Energy Projects Near You

Leaps Rigg Solar Farm (49.9 MW)

Leaps Rigg Solar Farm is a 49.9 MW solar farm project in Cumberland, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 28 September 2023, not yet built; the record was last updated on 19 February 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWsolar farm
approved, not builtstatus in REPD
19 February 2026record last updated
Cumberlandcouncil area

Planning timeline

DateStage
19 June 2023Application submitted
28 September 2023Planning permission granted
28 September 2026Permission expired

Project details

Technology
solar farm
Capacity
49.9 MW
Status (REPD)
approved, not built
Record last updated
19 February 2026
Operator or applicant
Opdenergy UK 7 Limited
Planning authority
Cumberland
Planning application reference
23/0415
Site area
91.5 ha
Address (REPD)
Leaps Rigg, Walton, Brampton
Council area (by location)
Cumberland
Time to decision
14 weeks
Contracts for Difference
AR7a
Name in REPD
Leaps Rigg - Solar Farm
REPD reference
8526

Who decides

ApplicationsCumberlandUK
Decided applications (solar, wind, battery)9110,236
Refused30 (33%)19%
Solar refused4 of 3212%
Onshore wind refused25 of 4545%
Battery storage refused1 of 1416%
Median time from submission to decision22.4 weeks17.0 weeks
Appeals lodged / allowed7 / 9—

Other large projects within 10 km

ProjectTypeMWStatuskm
High Parkfoot Farmsolar farm20approved, not built6.0
Hallburn Farmwind farm13.2operational9.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.0015, -2.7696).