Hallburn Farm (13.2 MW wind farm)
Hallburn Farm is a 13.2 MW wind farm project in Cumberland, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 15 February 2018; the record was last updated on 29 May 2018.
13.2 MWwind farm
operationalstatus in REPD
29 May 2018record last updated
Cumberlandcouncil area
Planning timeline
| Date | Stage |
|---|---|
| 8 November 2013 | Application submitted |
| 27 October 2014 | Planning permission granted |
| 15 January 2017 | Construction started |
| 15 February 2018 | Operational |
Project details
- Technology
- wind farm
- Capacity
- 13.2 MW
- Status (REPD)
- operational
- Record last updated
- 29 May 2018
- Operator or applicant
- REG Windpower/ BlackRock
- Planning authority
- Cumberland
- Planning application reference
- 13/0865
- Turbines
- 6
- Address (REPD)
- Land at Hallburn Farm, Hallburn, Longtown, Carlisle,
- Council area (by location)
- Cumberland
- Time to decision
- 50 weeks
- REPD reference
- 4316
Earlier applications for this site
| Application | MW | Submitted | Outcome |
|---|---|---|---|
| Hallburn Farm 11/0118 | 12 | 15 March 2011 | refused 19 August 2011 |
Who decides
| Applications | Cumberland | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 91 | 10,236 |
| Refused | 30 (33%) | 19% |
| Solar refused | 4 of 32 | 12% |
| Onshore wind refused | 25 of 45 | 45% |
| Battery storage refused | 1 of 14 | 16% |
| Median time from submission to decision | 22.4 weeks | 17.0 weeks |
| Appeals lodged / allowed | 7 / 9 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Todhills and Westlinton - Harker Battery Energy Storage Facility | battery storage | 200 | approved, not built | 5.9 |
| Beck Burn | wind farm | 31 | operational | 7.1 |
| Blackdyke Farm, Blackford | battery storage | 400 | approved, not built | 7.1 |
| Blackdyke Farm, Blackford | battery storage | 340 | refused | 7.1 |
| Blackdyke Farm | solar farm | 7.7 | abandoned | 7.4 |
| Low Harker Farm, Low Harker | battery storage | 400 | approved, not built | 7.6 |
| Blackdyke Farm Battery Storage Project | battery storage | 49.9 | abandoned | 7.8 |
| Harker Grid Sub Station | battery storage | 49.9 | permission expired | 8.1 |
| Harker Moss | battery storage | 360 | approved, not built | 8.1 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.0096, -2.9153).