Harker Moss (360 MW battery storage)

Harker Moss is a 360 MW battery storage project in Cumberland, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 9 July 2025, not yet built; the record was last updated on 7 May 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

360 MWbattery storage
approved, not builtstatus in REPD
7 May 2026record last updated
Cumberlandcouncil area

Planning timeline

DateStage
11 November 2024Application submitted
9 July 2025Planning permission granted

Project details

Technology
battery storage (stand-alone storage)
Capacity
360 MW
Status (REPD)
approved, not built
Record last updated
7 May 2026
Operator or applicant
ESB (Harker) Limited
Planning authority
Cumberland
Planning application reference
24/0680
Address (REPD)
Adj To Harker Substation Known As Harker Moss, Carlisle
Council area (by location)
Cumberland
Time to decision
34 weeks
Name in REPD
Harker Moss - Battery Energy Storage System
REPD reference
17649

Who decides

ApplicationsCumberlandUK
Decided applications (solar, wind, battery)9110,236
Refused30 (33%)19%
Solar refused4 of 3212%
Onshore wind refused25 of 4545%
Battery storage refused1 of 1416%
Median time from submission to decision22.4 weeks17.0 weeks
Appeals lodged / allowed7 / 9—

Other large projects within 10 km

ProjectTypeMWStatuskm
Harker Grid Sub Stationbattery storage49.9permission expired<0.1
Blackdyke Farm Battery Storage Projectbattery storage49.9abandoned0.4
Low Harker Farm, Low Harkerbattery storage400approved, not built0.6
Heathlandssolar farm5abandoned1.1
Blackdyke Farmsolar farm7.7abandoned1.1
Blackdyke Farm, Blackfordbattery storage340refused1.3
Blackdyke Farm, Blackfordbattery storage400approved, not built1.3
Kingmoor Parksolar farm5operational1.4
Cargo Road, Cargobattery storage200abandoned2.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.942, -2.964).