Harker Grid Sub Station (49.9 MW battery storage)

Harker Grid Sub Station is a 49.9 MW battery storage project in Cumberland, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: planning permission expired on 10 July 2022; the record was last updated on 17 September 2020.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWbattery storage
permission expiredstatus in REPD
17 September 2020record last updated
Cumberlandcouncil area

Planning timeline

DateStage
8 May 2019Application submitted
10 July 2019Planning permission granted
10 July 2022Permission expired

Project details

Technology
battery storage (stand-alone storage)
Capacity
49.9 MW
Status (REPD)
permission expired
Record last updated
17 September 2020
Operator or applicant
Pivot Power
Planning authority
Cumberland
Planning application reference
19/0371
Address (REPD)
Land to the west of Harker Grid Sub Station, Low Harker, Harker, Carlisle
Council area (by location)
Cumberland
Time to decision
9 weeks
REPD reference
7462

Who decides

ApplicationsCumberlandUK
Decided applications (solar, wind, battery)9110,236
Refused30 (33%)19%
Solar refused4 of 3212%
Onshore wind refused25 of 4545%
Battery storage refused1 of 1416%
Median time from submission to decision22.4 weeks17.0 weeks
Appeals lodged / allowed7 / 9—

Other large projects within 10 km

ProjectTypeMWStatuskm
Harker Mossbattery storage360approved, not built<0.1
Blackdyke Farm Battery Storage Projectbattery storage49.9abandoned0.3
Low Harker Farm, Low Harkerbattery storage400approved, not built0.6
Blackdyke Farmsolar farm7.7abandoned1.0
Heathlandssolar farm5abandoned1.1
Blackdyke Farm, Blackfordbattery storage400approved, not built1.3
Blackdyke Farm, Blackfordbattery storage340refused1.3
Kingmoor Parksolar farm5operational1.4
Cargo Road, Cargobattery storage200abandoned2.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.9423, -2.964).