Cargo Road, Cargo (200 MW battery storage)

Cargo Road, Cargo is a 200 MW battery storage project in Cumberland, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: abandoned; the record was last updated on 31 March 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

200 MWbattery storage
abandonedstatus in REPD
31 March 2026record last updated
Cumberlandcouncil area

Planning timeline

DateStage
14 September 2023Application submitted
17 October 2024Planning permission granted

Project details

Technology
battery storage (stand-alone storage)
Capacity
200 MW
Status (REPD)
abandoned
Record last updated
31 March 2026
Operator or applicant
Immersa Limited
Planning authority
Cumberland
Planning application reference
23/0613
Address (REPD)
Land to the south of Cargo Beck House, Cargo, Carlisle
Council area (by location)
Cumberland
Time to decision
57 weeks
Name in REPD
Cargo Road, Cargo - Battery Storage
REPD reference
14939

Who decides

ApplicationsCumberlandUK
Decided applications (solar, wind, battery)9110,236
Refused30 (33%)19%
Solar refused4 of 3212%
Onshore wind refused25 of 4545%
Battery storage refused1 of 1416%
Median time from submission to decision22.4 weeks17.0 weeks
Appeals lodged / allowed7 / 9—

Other large projects within 10 km

ProjectTypeMWStatuskm
Kingmoor Parksolar farm5operational0.9
Harker Mossbattery storage360approved, not built2.3
Harker Grid Sub Stationbattery storage49.9permission expired2.4
Heathlandssolar farm5abandoned2.4
Blackdyke Farm Battery Storage Projectbattery storage49.9abandoned2.6
Low Harker Farm, Low Harkerbattery storage400approved, not built2.9
Blackdyke Farmsolar farm7.7abandoned3.2
Blackdyke Farm, Blackfordbattery storage340refused3.5
Blackdyke Farm, Blackfordbattery storage400approved, not built3.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.9229, -2.9791).