Blackdyke Farm Battery Storage Project (49.9 MW)

Blackdyke Farm Battery Storage Project is a 49.9 MW battery storage project in Cumberland, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: abandoned; the record was last updated on 27 May 2020.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWbattery storage
abandonedstatus in REPD
27 May 2020record last updated
Cumberlandcouncil area

Planning timeline

DateStage
7 July 2017Application submitted

Project details

Technology
battery storage (co-located with re)
Capacity
49.9 MW
Status (REPD)
abandoned
Record last updated
27 May 2020
Operator or applicant
Low Carbon Storage Investment Company
Planning authority
Cumberland
Planning application reference
17/0616
Address (REPD)
Blackdyke Farmhouse Blackford, Road Leading From Tewthwaite Green North to Junction West of Justicetown
Council area (by location)
Cumberland
REPD reference
6999

Who decides

ApplicationsCumberlandUK
Decided applications (solar, wind, battery)9110,236
Refused30 (33%)19%
Solar refused4 of 3212%
Onshore wind refused25 of 4545%
Battery storage refused1 of 1416%
Median time from submission to decision22.4 weeks17.0 weeks
Appeals lodged / allowed7 / 9—

Other large projects within 10 km

ProjectTypeMWStatuskm
Harker Grid Sub Stationbattery storage49.9permission expired0.3
Harker Mossbattery storage360approved, not built0.4
Low Harker Farm, Low Harkerbattery storage400approved, not built0.5
Blackdyke Farmsolar farm7.7abandoned0.7
Blackdyke Farm, Blackfordbattery storage340refused0.9
Blackdyke Farm, Blackfordbattery storage400approved, not built0.9
Heathlandssolar farm5abandoned1.0
Kingmoor Parksolar farm5operational1.7
Todhills and Westlinton - Harker Battery Energy Storage Facilitybattery storage200approved, not built2.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.9452, -2.9652).