Blackdyke Farm, Blackford (400 MW battery storage)

Blackdyke Farm, Blackford is a 400 MW battery storage project in Cumberland, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 5 October 2023, not yet built; the record was last updated on 25 October 2023.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

400 MWbattery storage
approved, not builtstatus in REPD
25 October 2023record last updated
Cumberlandcouncil area

Planning timeline

DateStage
21 June 2023Application submitted
5 October 2023Planning permission granted
5 October 2026Permission expired

Project details

Technology
battery storage (stand-alone storage)
Capacity
400 MW
Status (REPD)
approved, not built
Record last updated
25 October 2023
Operator or applicant
Innova Renewables
Planning authority
Cumberland
Planning application reference
23/0444
Address (REPD)
West of Blackdyke Farm, Blackford
Council area (by location)
Cumberland
Time to decision
15 weeks
Name in REPD
Blackdyke Farm, Blackford - Battery Storage
REPD reference
15005

Who decides

ApplicationsCumberlandUK
Decided applications (solar, wind, battery)9110,236
Refused30 (33%)19%
Solar refused4 of 3212%
Onshore wind refused25 of 4545%
Battery storage refused1 of 1416%
Median time from submission to decision22.4 weeks17.0 weeks
Appeals lodged / allowed7 / 9—

Other large projects within 10 km

ProjectTypeMWStatuskm
Blackdyke Farm, Blackfordbattery storage340refused<0.1
Blackdyke Farmsolar farm7.7abandoned0.3
Blackdyke Farm Battery Storage Projectbattery storage49.9abandoned0.9
Low Harker Farm, Low Harkerbattery storage400approved, not built1.1
Heathlandssolar farm5abandoned1.3
Harker Grid Sub Stationbattery storage49.9permission expired1.3
Harker Mossbattery storage360approved, not built1.3
Todhills and Westlinton - Harker Battery Energy Storage Facilitybattery storage200approved, not built1.3
Kingmoor Parksolar farm5operational2.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.9535, -2.9682).