Energy Projects Near You

Solar, wind and battery projects near Canonbie (DG14)

7 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of DG14 (Dumfries and Galloway): 3 are waiting for a planning decision, 1 approved but not yet running, 3 operational. The largest live scheme is Gretna Green Battery Storage (456 MW battery storage, approved on 17 March 2025, not yet built), 7.5 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

7projects within 10 km
3awaiting a decision
1approved, not running
3operational

Projects within 10 km of DG14

Projects of 1 MW and more (6)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Bloch Wind Farm & Battery Storage (Solway Bank Extension)wind farmwind farm126application submitted may be out of dateupdated Apr 2022Nov 2022—Apr 2022Dumfries and Galloway6.7
Bloch Wind Farm & Battery Storage (Solway Bank Extension)battery storagebattery storage45application submitted may be out of dateupdated Sep 2025Nov 2022—Sep 2025Dumfries and Galloway6.7
Gretna Green Battery Storagebattery storagebattery storage456approved, not builtupdated May 2025Apr 2024granted Mar 2025May 2025Dumfries and Galloway7.5
Solwaybank Wind Farmwind farmwind farm30operationalupdated May 2022Nov 2011granted Sep 2014May 2022Dumfries and Galloway8.2
Beck Burnwind farmwind farm31operationalupdated May 2017Nov 2013granted Apr 2015May 2017Cumberland8.4
Hallburn Farmwind farmwind farm13.2operationalupdated May 2018Nov 2013granted Oct 2014May 2018Cumberland9.1
Smaller schemes under 1 MW, mostly rooftop solar (1)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Wind Farm at Appin Wind Farmwind farmwind farm—application submittedupdated Jul 2025Jun 2025—Jul 2025Dumfries and Galloway7.7

Distance from the average position of the DG14 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Wind farm52030126
Battery storage21100501

MW in pipeline: pending, approved and under-construction capacity.

How Dumfries and Galloway decides solar, wind and battery applications

ApplicationsDumfries and GallowayUK
Decided applications (solar, wind, battery)10610,236
Refused40 (38%)19%
Solar refused1 of 1812%
Onshore wind refused33 of 7245%
Battery storage refused6 of 1616%
Median time from submission to decision60.9 weeks17.0 weeks
Appeals lodged / allowed19 / 17—

All projects in Dumfries and Galloway

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near DG14, 2 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.