Energy Projects Near You

Solar, wind and battery projects near Annan (DG12)

7 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of DG12 (Dumfries and Galloway): 3 are waiting for a planning decision, 2 approved but not yet running. The largest live scheme is Jockstown Farm Solar Farm (37.9 MW solar farm, approved on 22 November 2022, not yet built; REPD status may be out of date), 4.5 km away. Offshore, 1 wind farm is recorded within 40 km; the nearest is Robin Rigg East (84 MW, operational), 38.0 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

7projects within 10 km
3awaiting a decision
2approved, not running
0operational

Projects within 10 km of DG12

Projects of 1 MW and more (5)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Jockstown Farm Solar Farmsolar farmsolar farm37.9approved, not built may be out of dateupdated Mar 2026Jan 2022granted Nov 2022Mar 2026Dumfries and Galloway4.5
West Scales Wind Farmwind farmwind farm16.5application withdrawnupdated Jan 2016Dec 2014—Jan 2016Dumfries and Galloway6.6
West Scales Energy Parkbattery storagebattery storage12application submittedupdated Jun 2026May 2026—Jun 2026Dumfries and Galloway7.4
West Scales Energy Parkwind farmwind farm24.8application submittedupdated Jun 2026May 2026—Jun 2026Dumfries and Galloway7.5
West Scales Energy Parksolar farmsolar farm12application submittedupdated Jun 2026May 2026—Jun 2026Dumfries and Galloway7.5
Smaller schemes under 1 MW, mostly rooftop solar (2)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Tesco Superstore Annanrooftop solarrooftop solar0.2permission expiredupdated Apr 2021Nov 2019granted Apr 2022Apr 2021Dumfries and Galloway0.4
Cochran Limited, Three Trees Roadsolar farmsolar farm0.5approved, not builtupdated Dec 2023Jun 2023granted Dec 2023Dec 2023Dumfries and Galloway2.5

Distance from the average position of the DG12 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm3120050.4
Rooftop solar100000
Wind farm2100024.8
Battery storage1100012

MW in pipeline: pending, approved and under-construction capacity.

Offshore wind farms within 40 km

Wind farmMWStatus (REPD)km
Robin Rigg East84operationalupdated Aug 201738.0

Operational, approved and pending offshore wind farms; distance from the district centre to the REPD grid reference of each wind farm (one point per site, so the nearest turbines can be closer or further). All offshore wind farms in UK waters.

How Dumfries and Galloway decides solar, wind and battery applications

ApplicationsDumfries and GallowayUK
Decided applications (solar, wind, battery)10610,236
Refused40 (38%)19%
Solar refused1 of 1812%
Onshore wind refused33 of 7245%
Battery storage refused6 of 1616%
Median time from submission to decision60.9 weeks17.0 weeks
Appeals lodged / allowed19 / 17—

All projects in Dumfries and Galloway

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near DG12, 1 project has a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.