Energy Projects Near You

Jockstown Farm Solar Farm (37.9 MW)

Jockstown Farm Solar Farm is a 37.9 MW solar farm project in Dumfries and Galloway, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 22 November 2022, not yet built; the record was last updated on 31 March 2026. REPD also records that the planning permission expired on 22 November 2025, so the project may not go ahead in this form. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

37.9 MWsolar farm
approved, not builtmay be out of datestatus in REPD
31 March 2026record last updated
Dumfries and Gallowaycouncil area

REPD also records that the planning permission expired on 22 November 2025, so the project may not go ahead in this form.

Planning timeline

DateStage
27 January 2022Application submitted
22 November 2022Planning permission granted
22 November 2025Permission expired

Project details

Technology
solar farm
Capacity
37.9 MW
Status (REPD)
approved, not built
Record last updated
31 March 2026
Operator or applicant
Green Energy International
Planning authority
Dumfries and Galloway
Planning application reference
21/2491/FUL
Site area
60.3 ha
Address (REPD)
Jockstown Farm Annan
Council area (by location)
Dumfries and Galloway
Time to decision
43 weeks
REPD reference
8488

Who decides

ApplicationsDumfries and GallowayUK
Decided applications (solar, wind, battery)10610,236
Refused40 (38%)19%
Solar refused1 of 1812%
Onshore wind refused33 of 7245%
Battery storage refused6 of 1616%
Median time from submission to decision60.9 weeks17.0 weeks
Appeals lodged / allowed19 / 17—

Other large projects within 10 km

ProjectTypeMWStatuskm
West Scales Wind Farmwind farm16.5application withdrawn6.3
West Scales Energy Parkbattery storage12application submitted7.0
West Scales Energy Parkwind farm24.8application submitted7.2
West Scales Energy Parksolar farm12application submitted7.2
Newfieldwind farm63refused7.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.0288, -3.2305).