Energy Projects Near You

Solar, wind and battery projects near Lockerbie (DG11)

11 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of DG11 (Dumfries and Galloway): 2 are waiting for a planning decision, 2 approved but not yet running, 3 operational. The largest live scheme is Arla Lockerbie Creamery Solar Farm (5 MW solar farm, application submitted on 9 March 2026, no decision recorded), 4.6 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

11projects within 10 km
2awaiting a decision
2approved, not running
3operational

Projects within 10 km of DG11

Projects of 1 MW and more (7)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Ewe Hill (extension)wind farmwind farm36.8operationalupdated Jul 2017Mar 2004granted May 2014Jul 2017Dumfries and Galloway0.8
Ewe Hillwind farmwind farm13.8operationalupdated Oct 2016Apr 2004granted Jun 2010Oct 2016Dumfries and Galloway0.8
Minscawind farmwind farm36.8operationalupdated Sep 2014Aug 2003granted Jun 2004Sep 2014Dumfries and Galloway1.3
Newfieldwind farmwind farm63refusedupdated Jul 2014Oct 2009refused Jun 2014Jul 2014Dumfries and Galloway4.6
Arla Lockerbie Creamery Solar Farmsolar farmsolar farm5application submittedupdated Mar 2026Mar 2026—Mar 2026Dumfries and Galloway4.6
Little Hartfell Wind Farmwind farmwind farm50.4application withdrawnupdated Mar 2022Oct 2020—Mar 2022Dumfries and Galloway7.9
Land At Hartwood Hillwind farmwind farm21application withdrawnupdated Jan 2016Jan 2015—Jan 2016Dumfries and Galloway8.4
Smaller schemes under 1 MW, mostly rooftop solar (4)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Rammerscales Sawmill Solar Array & Battery Storagebattery storagebattery storage—approved, not builtupdated Feb 2025Nov 2024granted Feb 2025Feb 2025Dumfries and Galloway7.0
Rammerscales Sawmill Solar Array & Battery Storagesolar farmsolar farm0.5approved, not builtupdated Feb 2025Nov 2024granted Feb 2025Feb 2025Dumfries and Galloway7.2
James Jones And Sons, Johnstonebridgerooftop solarrooftop solar0.3application submitted may be out of dateupdated Jun 2024May 2024—Jun 2024Dumfries and Galloway9.5
James And Sons, Johnstonebridgerooftop solarrooftop solar0.2application withdrawnupdated Aug 2023Nov 2022—Aug 2023Dumfries and Galloway9.7

Distance from the average position of the DG11 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm211005.5
Rooftop solar210000.3
Wind farm600310
Battery storage101000

MW in pipeline: pending, approved and under-construction capacity.

How Dumfries and Galloway decides solar, wind and battery applications

ApplicationsDumfries and GallowayUK
Decided applications (solar, wind, battery)10610,236
Refused40 (38%)19%
Solar refused1 of 1812%
Onshore wind refused33 of 7245%
Battery storage refused6 of 1616%
Median time from submission to decision60.9 weeks17.0 weeks
Appeals lodged / allowed19 / 17—

All projects in Dumfries and Galloway

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near DG11, 1 project has a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.