Energy Projects Near You

Solar, wind and battery projects near Dumfries (DG2)

7 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of DG2 (Dumfries and Galloway): 1 is waiting for a planning decision, 5 approved but not yet running. The largest live scheme is Harestanes South Windfarm Extension (45 MW wind farm, application submitted on 7 December 2020, no decision recorded; REPD status may be out of date), 3.2 km away. Offshore, 2 wind farms are recorded within 40 km; the nearest is Robin Rigg East (84 MW, operational), 33.5 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

7projects within 10 km
1awaiting a decision
5approved, not running
0operational

Projects within 10 km of DG2

Projects of 1 MW and more (3)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Harestanes South Windfarm Extensionwind farmwind farm45application submitted may be out of dateupdated Apr 2022Dec 2020—Apr 2022Dumfries and Galloway3.2
Kellwood Roadbattery storagebattery storage40approved, not builtupdated May 2025Jun 2024granted Apr 2025May 2025Dumfries and Galloway4.2
Barnbackle Windfarmwind farmwind farm5refusedupdated Sep 2014Jan 2007refused Nov 2011Sep 2014Dumfries and Galloway7.2
Smaller schemes under 1 MW, mostly rooftop solar (4)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Tesco Extra Dumfriesrooftop solarrooftop solar0.8approved, not built may be out of dateupdated Jun 2023May 2023granted Jul 2023Jun 2023Dumfries and Galloway2.4
Kellwood Roadrooftop solarrooftop solar0.2approved, not built may be out of dateupdated Jan 2023Nov 2022granted Jan 2023Jan 2023Dumfries and Galloway4.5
Lochar Industrial Estate Solar Panels & Battery Storagebattery storagebattery storage—approved, not builtupdated Feb 2025Nov 2024granted Jan 2025Feb 2025Dumfries and Galloway7.1
Lochar Industrial Estate Solar Panels & Battery Storagesolar farmsolar farm0.2approved, not builtupdated Feb 2025Nov 2024granted Jan 2025Feb 2025Dumfries and Galloway7.2

Distance from the average position of the DG2 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm101000.2
Rooftop solar202000.9
Wind farm2100145
Battery storage2020040

MW in pipeline: pending, approved and under-construction capacity.

Offshore wind farms within 40 km

Wind farmMWStatus (REPD)km
Robin Rigg East84operationalupdated Aug 201733.5
Robin Rigg West90operationalupdated Aug 201735.6

Operational, approved and pending offshore wind farms; distance from the district centre to the REPD grid reference of each wind farm (one point per site, so the nearest turbines can be closer or further). All offshore wind farms in UK waters.

How Dumfries and Galloway decides solar, wind and battery applications

ApplicationsDumfries and GallowayUK
Decided applications (solar, wind, battery)10610,236
Refused40 (38%)19%
Solar refused1 of 1812%
Onshore wind refused33 of 7245%
Battery storage refused6 of 1616%
Median time from submission to decision60.9 weeks17.0 weeks
Appeals lodged / allowed19 / 17—

All projects in Dumfries and Galloway

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near DG2, 3 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.