Kellwood Road (40 MW battery storage)

Kellwood Road is a 40 MW battery storage project in Dumfries and Galloway, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 15 April 2025, not yet built; the record was last updated on 6 May 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

40 MWbattery storage
approved, not builtstatus in REPD
6 May 2025record last updated
Dumfries and Gallowaycouncil area

Planning timeline

DateStage
28 June 2024Application submitted
15 April 2025Planning permission granted
15 April 2030Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
40 MW
Status (REPD)
approved, not built
Record last updated
6 May 2025
Operator or applicant
Geocore Limited
Planning authority
Dumfries and Galloway
Planning application reference
24/1075/FUL
Address (REPD)
Kellwood Road
Council area (by location)
Dumfries and Galloway
Time to decision
42 weeks
Name in REPD
Kellwood Road - Battery Storage
REPD reference
16540

Earlier applications for this site

ApplicationMWSubmittedOutcome
Kellwood Road 23/0513/FUL49.93 April 2023replaced by a revised application

Who decides

ApplicationsDumfries and GallowayUK
Decided applications (solar, wind, battery)10610,236
Refused40 (38%)19%
Solar refused1 of 1812%
Onshore wind refused33 of 7245%
Battery storage refused6 of 1616%
Median time from submission to decision60.9 weeks17.0 weeks
Appeals lodged / allowed19 / 17—

Other large projects within 10 km

ProjectTypeMWStatuskm
Harestanes South Windfarm Extensionwind farm45application submitted1.1
Land At Hartwood Hillwind farm21application withdrawn8.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.0684, -3.5929).