Robin Rigg West offshore wind farm

Robin Rigg West is a 90 MW offshore wind farm with 30 turbines in Scottish waters. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 18 July 2009; the record was last updated on 18 August 2017. Its REPD grid reference is 12 km from the nearest postcode on land (DG7 1RJ, Dumfries and Galloway). As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36.

How it works ↓

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

90 MWoffshore wind farm
operationalstatus in REPD
18 August 2017record last updated
12 km from land (Dumfries and Galloway)REPD location

Consent timeline

DateStage
14 June 2002Application submitted
16 June 2003Section 36 consent granted (Scottish Ministers)
1 December 2006Construction started
18 July 2009Operational

Project details

Technology
offshore wind farm
Capacity
90 MW
Turbines
30
Turbine capacity
3 MW
Status (REPD)
operational
Record last updated
18 August 2017
Operator or applicant
E.ON UK
Consenting authority (REPD)
Scottish Government (S36)
Application reference
not recorded
Nearest postcode on land
DG7 1RJ (Dumfries and Galloway), 11.9 km from the REPD grid reference
Time to decision
52 weeks
REPD reference
2497

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36.

Postcode districts within 40 km

Districtkm
Maryport (CA15)16.4
Workington (CA14)17.6
Dalbeattie (DG5)20.1
Kirkcudbright (DG6)23.2
Whitehaven (CA28)24.7
Cockermouth (CA13)25.2
Frizington (CA26)27.6
Cleator Moor (CA25)28.4
Moor Row (CA24)28.4
St Bees (CA27)29.8
Cleator (CA23)29.9
Castle Douglas (DG7)30.7

Straight-line distance from the centre of each postcode district to the REPD grid reference of the wind farm, which is a single point for the whole site.

Other offshore wind projects within 30 km

ProjectMWStatuskm
Robin Rigg East84operational2.9

All offshore wind farms in UK waters

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database can lag behind consent decisions. Location: REPD grid reference (54.7473, -3.7293).

In the REPD the Robin Rigg wind farm is recorded twice. Robin Rigg West is 30 turbines of 3 MW each, and Robin Rigg East, 2.9 km away, adds another 28 identical turbines and 84 MW; together that comes to 174 MW, with E.ON UK as the applicant for both records. Their application and consent dates are shared, but the commissioning dates differ: West has been operational since 18 July 2009, East since 28 April 2010.

An early farm between two shores

The application was submitted on 14 June 2002, and Scottish Ministers granted consent under Section 36 as early as 16 June 2003: 52 weeks against a median of 81.1 for decisions of this kind. Construction ran from 1 December 2006. The farm sits in the Solway Firth. The consent is Scottish, and the nearest postcode on land is DG7 1RJ in Dumfries and Galloway (11.9 km), but the nearest districts include the English shore too: Maryport (16.4 km) and Workington (17.6 km) in Cumbria. On the Scottish side, Dalbeattie is closer. The West and East records were last updated on 18 August 2017.