In the REPD the Robin Rigg wind farm is recorded twice. Robin Rigg West is 30 turbines of 3 MW each, and Robin Rigg East, 2.9 km away, adds another 28 identical turbines and 84 MW; together that comes to 174 MW, with E.ON UK as the applicant for both records. Their application and consent dates are shared, but the commissioning dates differ: West has been operational since 18 July 2009, East since 28 April 2010.
An early farm between two shores
The application was submitted on 14 June 2002, and Scottish Ministers granted consent under Section 36 as early as 16 June 2003: 52 weeks against a median of 81.1 for decisions of this kind. Construction ran from 1 December 2006. The farm sits in the Solway Firth. The consent is Scottish, and the nearest postcode on land is DG7 1RJ in Dumfries and Galloway (11.9 km), but the nearest districts include the English shore too: Maryport (16.4 km) and Workington (17.6 km) in Cumbria. On the Scottish side, Dalbeattie is closer. The West and East records were last updated on 18 August 2017.