Solar, wind and battery projects near Cockermouth (CA13)

15 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of CA13 (Cumberland): 1 is waiting for a planning decision, 4 approved but not yet running, 6 operational. The largest live scheme is Ewanrigg Farmhouse, Ewanrigg Solar Farm (13 MW solar farm, approved on 3 June 2026, not yet built), 9.1 km away. Offshore, 2 wind farms are recorded within 40 km; the nearest is Robin Rigg East (84 MW, operational), 24.0 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

15projects within 10 km
1awaiting a decision
4approved, not running
6operational

Projects within 10 km of CA13

Projects of 1 MW and more (10)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Former Broughton Lodge Resubmissionwind farmwind farm9refusedupdated Feb 2011Dec 2009—Feb 2011Cumberland3.1
Fleeter Wood Wind Farmwind farmwind farm10abandonedupdated Mar 2009Dec 2007granted Jan 2009Mar 2009Cumberland5.2
Tallentire Hillwind farmwind farm12operationalupdated Jun 2014Mar 2008granted Feb 2011Jun 2014Cumberland5.2
Winscales Moorwind farmwind farm6operationalupdated Dec 2017Oct 2006granted Jun 2007Dec 2017Cumberland8.5
Ewanrigg Farmhouse, Ewanrigg Solar Farmsolar farmsolar farm13approved, not builtupdated Jun 2026Jun 2025granted Jun 2026Jun 2026Cumberland9.1
Wharrels Hill Wind Farmwind farmwind farm10.4operationalupdated May 2009Dec 2000granted Jun 2002May 2009Cumberland9.2
Winscales Phase I and IIwind farmwind farm8.8operationalupdated Sep 2009Nov 1997granted Jun 1999Sep 2009Cumberland9.4
Threapland Leeswind farmwind farm12application withdrawnupdated Oct 2011Oct 2009—Oct 2011Cumberland9.8
Land at Flimby Hall Farmwind farmwind farm6.2operationalupdated Jun 2013Jun 2009granted Jun 2010Jun 2013Cumberland9.9
Wharrels Hillsolar farmsolar farm14.6appeal withdrawnupdated Aug 2018Aug 2014refused Jul 2015Aug 2018Cumberland10.0
Smaller schemes under 1 MW, mostly rooftop solar (5)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
James Walker And Corooftop solarrooftop solar0.5approved, not builtupdated Mar 2022Mar 2022granted Apr 2022Mar 2022Cumberland0.9
M-Sport Limitedsolar farmsolar farm0.2approved, not built may be out of dateupdated Jan 2022Feb 2021granted Apr 2021Jan 2022Cumberland3.9
M Sport, Dovenby Hall Estaterooftop solarrooftop solar0.8operationalupdated Oct 2023Jan 2023granted Feb 2023Oct 2023Cumberland5.2
Telecommunication Site Moota - Micro Energy Storage Projectbattery storagebattery storage—application submittedJun 2026——Cumberland7.9
Ewanrigg Farmhouse, Ewanriggbattery storagebattery storage—approved, not builtupdated Jun 2026Jun 2025granted Jun 2026Jun 2026Cumberland9.1

Distance from the average position of the CA13 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm3020013.2
Rooftop solar201100.5
Wind farm800510
Battery storage211000

MW in pipeline: pending, approved and under-construction capacity.

Offshore wind farms within 40 km

Wind farmMWStatus (REPD)km
Robin Rigg East84operationalupdated Aug 201724.0
Robin Rigg West90operationalupdated Aug 201725.2

Operational, approved and pending offshore wind farms; distance from the district centre to the REPD grid reference of each wind farm (one point per site, so the nearest turbines can be closer or further). All offshore wind farms in UK waters.

How Cumberland decides solar, wind and battery applications

ApplicationsCumberlandUK
Decided applications (solar, wind, battery)9110,236
Refused30 (33%)19%
Solar refused4 of 3212%
Onshore wind refused25 of 4545%
Battery storage refused1 of 1416%
Median time from submission to decision22.4 weeks17.0 weeks
Appeals lodged / allowed7 / 9—

All projects in Cumberland

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near CA13, 1 project has a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.