Land at Flimby Hall Farm (6.2 MW wind farm)

Land at Flimby Hall Farm is a 6.2 MW wind farm project in Cumberland, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 14 June 2013; the record was last updated on 25 June 2013.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

6.2 MWwind farm
operationalstatus in REPD
25 June 2013record last updated
Cumberlandcouncil area

Planning timeline

DateStage
9 June 2009Application submitted
8 December 2009Refused by the planning authority
18 June 2010Planning permission granted
18 June 2010Appeal allowed
1 April 2012Construction started
14 June 2013Operational

Project details

Technology
wind farm
Capacity
6.2 MW
Status (REPD)
operational
Record last updated
25 June 2013
Operator or applicant
Flimby Wind Energy Ltd
Planning authority
Cumberland
Planning application reference
2/2009/0418
Appeal reference
APP/G0908/A/09/2118993/NWF
Turbines
3
Address (REPD)
Flimby, Maryport,
Council area (by location)
Cumberland
Time to decision
53 weeks
REPD reference
3972

Earlier applications for this site

ApplicationMWSubmittedOutcome
Land at Flimby Hall Farm 2/2007/12559.55 December 2007replaced by a revised application

Who decides

ApplicationsCumberlandUK
Decided applications (solar, wind, battery)9110,236
Refused30 (33%)19%
Solar refused4 of 3212%
Onshore wind refused25 of 4545%
Battery storage refused1 of 1416%
Median time from submission to decision22.4 weeks17.0 weeks
Appeals lodged / allowed7 / 9—

Other large projects within 10 km

ProjectTypeMWStatuskm
St Helen's Lanesolar farm5operational1.6
Ewanrigg Farmhouse, Ewanrigg Solar Farmsolar farm13approved, not built2.5
Iggesund Wind Farmwind farm9refused3.4
Oldside Wind Farmwind farm5.4operational4.1
Winscales Moorwind farm6operational5.1
Fleeter Wood Wind Farmwind farm10abandoned6.3
Winscales Phase I and IIwind farm8.8operational6.5
Former Broughton Lodge Resubmissionwind farm9refused6.7
Moorhouse Farmsolar farm5operational8.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.6871, -3.514).