Fleeter Wood Wind Farm (10 MW)
Fleeter Wood Wind Farm is a 10 MW wind farm project in Cumberland, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: abandoned; the record was last updated on 30 March 2009.
10 MWwind farm
abandonedstatus in REPD
30 March 2009record last updated
Cumberlandcouncil area
Planning timeline
| Date | Stage |
|---|---|
| 17 December 2007 | Application submitted |
| 29 January 2009 | Planning permission granted |
| 29 January 2017 | Permission expired |
Project details
- Technology
- wind farm
- Capacity
- 10 MW
- Status (REPD)
- abandoned
- Record last updated
- 30 March 2009
- Operator or applicant
- Novera Energy
- Planning authority
- Cumberland
- Planning application reference
- 2/2007/1271
- Turbines
- 5
- Address (REPD)
- Fleeter Wood, Land adjacent to West House, Dearham, Maryport, Cumbria, CA15 7LD
- Council area (by location)
- Cumberland
- Time to decision
- 58 weeks
- REPD reference
- 3053
Who decides
| Applications | Cumberland | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 91 | 10,236 |
| Refused | 30 (33%) | 19% |
| Solar refused | 4 of 32 | 12% |
| Onshore wind refused | 25 of 45 | 45% |
| Battery storage refused | 1 of 14 | 16% |
| Median time from submission to decision | 22.4 weeks | 17.0 weeks |
| Appeals lodged / allowed | 7 / 9 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Former Broughton Lodge Resubmission | wind farm | 9 | refused | 2.9 |
| Tallentire Hill | wind farm | 12 | operational | 3.9 |
| Ewanrigg Farmhouse, Ewanrigg Solar Farm | solar farm | 13 | approved, not built | 4.5 |
| Land at Flimby Hall Farm | wind farm | 6.2 | operational | 6.3 |
| St Helen's Lane | solar farm | 5 | operational | 7.4 |
| Winscales Moor | wind farm | 6 | operational | 7.9 |
| Threapland Lees | wind farm | 12 | application withdrawn | 8.8 |
| West Farm, Aspatria | battery storage | 50 | approved, not built | 8.9 |
| Lancarr | wind farm | 6.9 | application withdrawn | 9.0 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.6968, -3.4181).