Energy Projects Near You

Fleeter Wood Wind Farm (10 MW)

Fleeter Wood Wind Farm is a 10 MW wind farm project in Cumberland, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: abandoned; the record was last updated on 30 March 2009.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

10 MWwind farm
abandonedstatus in REPD
30 March 2009record last updated
Cumberlandcouncil area

Planning timeline

DateStage
17 December 2007Application submitted
29 January 2009Planning permission granted
29 January 2017Permission expired

Project details

Technology
wind farm
Capacity
10 MW
Status (REPD)
abandoned
Record last updated
30 March 2009
Operator or applicant
Novera Energy
Planning authority
Cumberland
Planning application reference
2/2007/1271
Turbines
5
Address (REPD)
Fleeter Wood, Land adjacent to West House, Dearham, Maryport, Cumbria, CA15 7LD
Council area (by location)
Cumberland
Time to decision
58 weeks
REPD reference
3053

Who decides

ApplicationsCumberlandUK
Decided applications (solar, wind, battery)9110,236
Refused30 (33%)19%
Solar refused4 of 3212%
Onshore wind refused25 of 4545%
Battery storage refused1 of 1416%
Median time from submission to decision22.4 weeks17.0 weeks
Appeals lodged / allowed7 / 9—

Other large projects within 10 km

ProjectTypeMWStatuskm
Former Broughton Lodge Resubmissionwind farm9refused2.9
Tallentire Hillwind farm12operational3.9
Ewanrigg Farmhouse, Ewanrigg Solar Farmsolar farm13approved, not built4.5
Land at Flimby Hall Farmwind farm6.2operational6.3
St Helen's Lanesolar farm5operational7.4
Winscales Moorwind farm6operational7.9
Threapland Leeswind farm12application withdrawn8.8
West Farm, Aspatriabattery storage50approved, not built8.9
Lancarrwind farm6.9application withdrawn9.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.6968, -3.4181).