Former Broughton Lodge Resubmission (9 MW wind farm)

Former Broughton Lodge Resubmission is a 9 MW wind farm project in Cumberland, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused; the record was last updated on 7 February 2011.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

9 MWwind farm
refusedstatus in REPD
7 February 2011record last updated
Cumberlandcouncil area

Planning timeline

DateStage
21 December 2009Application submitted

Project details

Technology
wind farm
Capacity
9 MW
Status (REPD)
refused
Record last updated
7 February 2011
Operator or applicant
Peel Energy
Planning authority
Cumberland
Planning application reference
2/2009/0880
Turbines
3
Address (REPD)
Great Broughton, Cockermouth, Cumbria. CA13 0LD
Council area (by location)
Cumberland
REPD reference
2712

Who decides

ApplicationsCumberlandUK
Decided applications (solar, wind, battery)9110,236
Refused30 (33%)19%
Solar refused4 of 3212%
Onshore wind refused25 of 4545%
Battery storage refused1 of 1416%
Median time from submission to decision22.4 weeks17.0 weeks
Appeals lodged / allowed7 / 9—

Other large projects within 10 km

ProjectTypeMWStatuskm
Fleeter Wood Wind Farmwind farm10abandoned2.9
Tallentire Hillwind farm12operational5.3
Ewanrigg Farmhouse, Ewanrigg Solar Farmsolar farm13approved, not built6.0
Winscales Moorwind farm6operational6.2
Land at Flimby Hall Farmwind farm6.2operational6.7
St Helen's Lanesolar farm5operational7.3
Winscales Phase I and IIwind farm8.8operational7.5
Iggesund Wind Farmwind farm9refused8.5
Lillyhall Wind Farmwind farm9.2refused9.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.6705, -3.4133).