Lillyhall Wind Farm (9.2 MW)

Lillyhall Wind Farm is a 9.2 MW wind farm project in Cumberland, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 28 February 2014; the record was last updated on 2 December 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

9.2 MWwind farm
refusedstatus in REPD
2 December 2015record last updated
Cumberlandcouncil area

Planning timeline

DateStage
30 October 2012Application submitted
28 February 2014Refused by the planning authority
14 April 2015Appeal lodged
3 November 2015Secretary of State refused

Project details

Technology
wind farm
Capacity
9.2 MW
Status (REPD)
refused
Record last updated
2 December 2015
Operator or applicant
FCC Environment
Planning authority
Cumberland
Planning application reference
02/2012/9011
Appeal reference
APP/H0900/A/14/2224323
Turbines
4
Address (REPD)
Lillyhall Landfill Site, Cumbria
Council area (by location)
Cumberland
Time to decision
69 weeks
REPD reference
3794

Who decides

ApplicationsCumberlandUK
Decided applications (solar, wind, battery)9110,236
Refused30 (33%)19%
Solar refused4 of 3212%
Onshore wind refused25 of 4545%
Battery storage refused1 of 1416%
Median time from submission to decision22.4 weeks17.0 weeks
Appeals lodged / allowed7 / 9—

Other large projects within 10 km

ProjectTypeMWStatuskm
Potato Pot Wind Farmwind farm6operational0.9
Moorhouse Farmsolar farm5operational1.5
Winscales Phase I and IIwind farm8.8operational2.1
Dean Moor Solar Farm & Battery Storagesolar farm150approved, not built2.5
Fairfield Farmwind farm6.5operational3.6
Winscales Moorwind farm6operational3.6
Fairfield Farmwind farm7.8application withdrawn3.6
Weddicar Rigg Wind Farmwind farm12refused on appeal5.7
Oldside Wind Farmwind farm5.4operational6.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.6103, -3.5081).