Fairfield Farm (6.5 MW wind farm)

Fairfield Farm is a 6.5 MW wind farm project in Cumberland, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 2 March 2011; the record was last updated on 6 June 2011.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

6.5 MWwind farm
operationalstatus in REPD
6 June 2011record last updated
Cumberlandcouncil area

Planning timeline

DateStage
29 September 2006Application submitted
4 April 2007Refused by the planning authority
20 May 2008Planning permission granted
20 May 2008Appeal allowed
1 August 2010Construction started
2 March 2011Operational

Project details

Technology
wind farm
Capacity
6.5 MW
Status (REPD)
operational
Record last updated
6 June 2011
Operator or applicant
Windprospect
Planning authority
Cumberland
Planning application reference
4/2006/2684
Turbines
5
Address (REPD)
Fairfield Farm, Pica, Distington
Council area (by location)
Cumberland
Time to decision
86 weeks
REPD reference
3613

Earlier applications for this site

ApplicationMWSubmittedOutcome
Fairfield Farm Wind Farm 04/95/05595.911 August 1995refused 1 April 1996

Who decides

ApplicationsCumberlandUK
Decided applications (solar, wind, battery)9110,236
Refused30 (33%)19%
Solar refused4 of 3212%
Onshore wind refused25 of 4545%
Battery storage refused1 of 1416%
Median time from submission to decision22.4 weeks17.0 weeks
Appeals lodged / allowed7 / 9—

Other large projects within 10 km

ProjectTypeMWStatuskm
Fairfield Farmwind farm7.8application withdrawn0.3
Weddicar Rigg Wind Farmwind farm12refused on appeal2.1
Potato Pot Wind Farmwind farm6operational2.9
Dean Moor Solar Farm & Battery Storagesolar farm150approved, not built3.4
Lillyhall Wind Farmwind farm9.2refused3.6
Moorhouse Farmsolar farm5operational4.0
Winscales Phase I and IIwind farm8.8operational5.7
Winscales Moorwind farm6operational7.2
Woodend And Moor Row, Egremontbattery storage30approved, not built7.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.5788, -3.5204).