Energy Projects Near You

Solar, wind and battery projects near Moor Row (CA24)

17 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of CA24 (Cumberland): 2 are waiting for a planning decision, 8 approved but not yet running, 3 operational. The largest live scheme is Dean Moor Solar Farm & Battery Storage (150 MW solar farm, approved on 2 July 2026, not yet built), 9.9 km away. Offshore, 2 wind farms are recorded within 40 km; the nearest is Robin Rigg West (90 MW, operational), 28.4 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

17projects within 10 km
2awaiting a decision
8approved, not running
3operational

Projects within 10 km of CA24

Projects of 1 MW and more (10)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Woodend And Moor Row, Egremontbattery storagebattery storage30approved, not builtupdated Jan 2026May 2025granted Dec 2025Jan 2026Cumberland0.8
Cleatorbattery storagebattery storage10operationalupdated Jan 2019——Jan 2019Cumberland1.6
Cleator Energy Storage Facility Extensionbattery storagebattery storage5application submittedupdated Feb 2026Jan 2026—Feb 2026Cumberland1.7
Cleator Solar Parksolar farmsolar farm5refused on appealupdated Jul 2016Aug 2014refused Oct 2015Jul 2016Cumberland1.7
Weddicar Rigg Wind Farmwind farmwind farm12refused on appealupdated Jun 2014Oct 2011refused Oct 2012Jun 2014Cumberland5.1
Yeorton Hall Farmsolar farmsolar farm5permission expiredupdated Jul 2020Sep 2015granted May 2016Jul 2020Cumberland6.9
Fairfield Farmwind farmwind farm7.8application withdrawnupdated Jun 2009Sep 2005—Jun 2009Cumberland7.2
Fairfield Farmwind farmwind farm6.5operationalupdated Jun 2011Sep 2006granted May 2008Jun 2011Cumberland7.2
Lowca Wind Farmwind farmwind farm4.7operationalupdated Jun 2009Jun 1998granted Mar 1999Jun 2009Cumberland9.3
Dean Moor Solar Farm & Battery Storagesolar farmsolar farm150approved, not builtupdated Jul 2026Mar 2025granted Jul 2026Jul 2026Cumberland9.9
Smaller schemes under 1 MW, mostly rooftop solar (7)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Highfield Farm, St Beeswind farmwind farm0.2approved, not builtupdated Nov 2025Sep 2024granted Oct 2025Nov 2025Cumberland2.5
Whitehaven Academyrooftop solarrooftop solar0.2approved, not builtupdated Feb 2026Nov 2025granted Jan 2026Feb 2026Cumberland2.8
J Dixon And Sons, Lowther Streetrooftop solarrooftop solar0.2approved, not builtupdated May 2025Feb 2025granted Apr 2025May 2025Cumberland4.5
The Energy Coast Business Park, Hailewind turbinewind turbine0.9application submitted may be out of dateupdated Mar 2024Feb 2024—Mar 2024Cumberland6.5
Stubsgill Farm, Distingtonwind turbinewind turbine0.2approved, not builtupdated Jul 2025Aug 2024granted Jun 2025Jul 2025Cumberland8.5
Griffin Park Tactical Training Facilityrooftop solarrooftop solar0.4approved, not builtupdated Mar 2025Oct 2024granted Feb 2025Mar 2025Cumberland9.5
Dean Moor Solar Farm & Battery Storagebattery storagebattery storage—approved, not builtupdated Jul 2026Mar 2025granted Jul 2026Jul 2026Cumberland9.9

Distance from the average position of the CA24 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm30101150
Rooftop solar303000.8
Wind farm501210.2
Wind turbine211001.2
Battery storage4121035

MW in pipeline: pending, approved and under-construction capacity.

Offshore wind farms within 40 km

Wind farmMWStatus (REPD)km
Robin Rigg West90operationalupdated Aug 201728.4
Robin Rigg East84operationalupdated Aug 201729.3

Operational, approved and pending offshore wind farms; distance from the district centre to the REPD grid reference of each wind farm (one point per site, so the nearest turbines can be closer or further). All offshore wind farms in UK waters.

How Cumberland decides solar, wind and battery applications

ApplicationsCumberlandUK
Decided applications (solar, wind, battery)9110,236
Refused30 (33%)19%
Solar refused4 of 3212%
Onshore wind refused25 of 4545%
Battery storage refused1 of 1416%
Median time from submission to decision22.4 weeks17.0 weeks
Appeals lodged / allowed7 / 9—

All projects in Cumberland

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near CA24, 1 project has a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.