Energy Projects Near You

Solar, wind and battery projects near St Bees (CA27)

11 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of CA27 (Cumberland): 2 are waiting for a planning decision, 5 approved but not yet running, 1 operational. The largest live scheme is Woodend And Moor Row, Egremont (30 MW battery storage, approved on 15 December 2025, not yet built), 4.5 km away. Offshore, 2 wind farms are recorded within 40 km; the nearest is Robin Rigg West (90 MW, operational), 29.8 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

11projects within 10 km
2awaiting a decision
5approved, not running
1operational

Projects within 10 km of CA27

Projects of 1 MW and more (6)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Cleator Solar Parksolar farmsolar farm5refused on appealupdated Jul 2016Aug 2014refused Oct 2015Jul 2016Cumberland4.2
Cleator Energy Storage Facility Extensionbattery storagebattery storage5application submittedupdated Feb 2026Jan 2026—Feb 2026Cumberland4.3
Cleatorbattery storagebattery storage10operationalupdated Jan 2019——Jan 2019Cumberland4.4
Woodend And Moor Row, Egremontbattery storagebattery storage30approved, not builtupdated Jan 2026May 2025granted Dec 2025Jan 2026Cumberland4.5
Yeorton Hall Farmsolar farmsolar farm5permission expiredupdated Jul 2020Sep 2015granted May 2016Jul 2020Cumberland6.4
Weddicar Rigg Wind Farmwind farmwind farm12refused on appealupdated Jun 2014Oct 2011refused Oct 2012Jun 2014Cumberland8.9
Smaller schemes under 1 MW, mostly rooftop solar (5)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Highfield Farm, St Beeswind farmwind farm0.2approved, not builtupdated Nov 2025Sep 2024granted Oct 2025Nov 2025Cumberland1.7
Whitehaven Academyrooftop solarrooftop solar0.2approved, not builtupdated Feb 2026Nov 2025granted Jan 2026Feb 2026Cumberland5.9
J Dixon And Sons, Lowther Streetrooftop solarrooftop solar0.2approved, not builtupdated May 2025Feb 2025granted Apr 2025May 2025Cumberland6.2
The Energy Coast Business Park, Hailewind turbinewind turbine0.9application submitted may be out of dateupdated Mar 2024Feb 2024—Mar 2024Cumberland6.5
Griffin Park Tactical Training Facilityrooftop solarrooftop solar0.4approved, not builtupdated Mar 2025Oct 2024granted Feb 2025Mar 2025Cumberland9.1

Distance from the average position of the CA27 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm200010
Rooftop solar303000.8
Wind farm201010.2
Wind turbine110000.9
Battery storage3111035

MW in pipeline: pending, approved and under-construction capacity.

Offshore wind farms within 40 km

Wind farmMWStatus (REPD)km
Robin Rigg West90operationalupdated Aug 201729.8
Robin Rigg East84operationalupdated Aug 201731.1

Operational, approved and pending offshore wind farms; distance from the district centre to the REPD grid reference of each wind farm (one point per site, so the nearest turbines can be closer or further). All offshore wind farms in UK waters.

How Cumberland decides solar, wind and battery applications

ApplicationsCumberlandUK
Decided applications (solar, wind, battery)9110,236
Refused30 (33%)19%
Solar refused4 of 3212%
Onshore wind refused25 of 4545%
Battery storage refused1 of 1416%
Median time from submission to decision22.4 weeks17.0 weeks
Appeals lodged / allowed7 / 9—

All projects in Cumberland

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near CA27, 1 project has a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.