Cleator Solar Park (5 MW)

Cleator Solar Park is a 5 MW solar farm project in Cumberland, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 15 June 2016; the record was last updated on 1 July 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
refused on appealstatus in REPD
1 July 2016record last updated
Cumberlandcouncil area

Planning timeline

DateStage
1 August 2014Application submitted
1 October 2015Refused by the planning authority
14 December 2015Appeal lodged
15 June 2016Appeal refused

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
refused on appeal
Record last updated
1 July 2016
Operator or applicant
Cleator Solar Park
Planning authority
Cumberland
Planning application reference
4/14/2336/0F1
Appeal reference
APP/Z0923/W/15/3138554
Address (REPD)
Land between Woodend and Moor Row, Egremont
Council area (by location)
Cumberland
Time to decision
61 weeks
REPD reference
5981

Who decides

ApplicationsCumberlandUK
Decided applications (solar, wind, battery)9110,236
Refused30 (33%)19%
Solar refused4 of 3212%
Onshore wind refused25 of 4545%
Battery storage refused1 of 1416%
Median time from submission to decision22.4 weeks17.0 weeks
Appeals lodged / allowed7 / 9—

Other large projects within 10 km

ProjectTypeMWStatuskm
Cleator Energy Storage Facility Extensionbattery storage5application submitted0.2
Cleatorbattery storage10operational0.3
Woodend And Moor Row, Egremontbattery storage30approved, not built1.2
Yeorton Hall Farmsolar farm5permission expired5.2
Weddicar Rigg Wind Farmwind farm12refused on appeal6.5
Fairfield Farmwind farm6.5operational8.6
Fairfield Farmwind farm7.8application withdrawn8.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.5014, -3.5315).