Yeorton Hall Farm (5 MW solar farm)

Yeorton Hall Farm is a 5 MW solar farm project in Cumberland, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: planning permission expired on 24 May 2019; the record was last updated on 29 July 2020.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
permission expiredstatus in REPD
29 July 2020record last updated
Cumberlandcouncil area

Planning timeline

DateStage
2 September 2015Application submitted
24 May 2016Planning permission granted
24 May 2019Permission expired

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
permission expired
Record last updated
29 July 2020
Operator or applicant
Green Energy UK Direct
Planning authority
Cumberland
Planning application reference
4/15/2377/0F1
Address (REPD)
Land at Yeorton Hall Farm, Oaklands, Egremont
Council area (by location)
Cumberland
Time to decision
38 weeks
REPD reference
5676

Who decides

ApplicationsCumberlandUK
Decided applications (solar, wind, battery)9110,236
Refused30 (33%)19%
Solar refused4 of 3212%
Onshore wind refused25 of 4545%
Battery storage refused1 of 1416%
Median time from submission to decision22.4 weeks17.0 weeks
Appeals lodged / allowed7 / 9—

Other large projects within 10 km

ProjectTypeMWStatuskm
Cleator Solar Parksolar farm5refused on appeal5.2
Cleator Energy Storage Facility Extensionbattery storage5application submitted5.3
Cleatorbattery storage10operational5.3
Woodend And Moor Row, Egremontbattery storage30approved, not built6.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.4561, -3.5143).