Energy Projects Near You

Cleator (10 MW battery storage)

Cleator is a 10 MW battery storage project in Cumberland, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 8 January 2018; the record was last updated on 3 January 2019.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

10 MWbattery storage
operationalstatus in REPD
3 January 2019record last updated
Cumberlandcouncil area

Planning timeline

DateStage
8 August 2017Construction started
8 January 2018Operational

Project details

Technology
battery storage (stand-alone storage)
Capacity
10 MW
Status (REPD)
operational
Record last updated
3 January 2019
Operator or applicant
Low Carbon Storage Investment Company/ VLC
Planning authority
Cumberland
Planning application reference
not recorded
Address (REPD)
Cleator, Cumbria
Council area (by location)
Cumberland
REPD reference
7177

Who decides

ApplicationsCumberlandUK
Decided applications (solar, wind, battery)9110,236
Refused30 (33%)19%
Solar refused4 of 3212%
Onshore wind refused25 of 4545%
Battery storage refused1 of 1416%
Median time from submission to decision22.4 weeks17.0 weeks
Appeals lodged / allowed7 / 9—

Other large projects within 10 km

ProjectTypeMWStatuskm
Cleator Energy Storage Facility Extensionbattery storage5application submitted0.1
Cleator Solar Parksolar farm5refused on appeal0.3
Woodend And Moor Row, Egremontbattery storage30approved, not built1.0
Yeorton Hall Farmsolar farm5permission expired5.3
Weddicar Rigg Wind Farmwind farm12refused on appeal6.3
Fairfield Farmwind farm6.5operational8.4
Fairfield Farmwind farm7.8application withdrawn8.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.5034, -3.5293).