Potato Pot Wind Farm (6 MW)

Potato Pot Wind Farm is a 6 MW wind farm project in Cumberland, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 15 September 2016; the record was last updated on 4 January 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

6 MWwind farm
operationalstatus in REPD
4 January 2017record last updated
Cumberlandcouncil area

Planning timeline

DateStage
7 August 2012Application submitted
25 January 2013Refused by the planning authority
23 October 2013Planning permission granted
23 October 2013Appeal allowed
15 September 2015Construction started
15 September 2016Operational

Project details

Technology
wind farm
Capacity
6 MW
Status (REPD)
operational
Record last updated
4 January 2017
Operator or applicant
Capital Dynamics
Planning authority
Cumberland
Planning application reference
2/2012/0594
Appeal reference
APP/G0908/A/13/2189934/NWF
Turbines
3
Address (REPD)
Land at Potato Pot Branthwaite Workington Cumbria
Council area (by location)
Cumberland
Time to decision
63 weeks
REPD reference
4233

Who decides

ApplicationsCumberlandUK
Decided applications (solar, wind, battery)9110,236
Refused30 (33%)19%
Solar refused4 of 3212%
Onshore wind refused25 of 4545%
Battery storage refused1 of 1416%
Median time from submission to decision22.4 weeks17.0 weeks
Appeals lodged / allowed7 / 9—

Other large projects within 10 km

ProjectTypeMWStatuskm
Lillyhall Wind Farmwind farm9.2refused0.9
Dean Moor Solar Farm & Battery Storagesolar farm150approved, not built1.8
Moorhouse Farmsolar farm5operational2.1
Fairfield Farmwind farm6.5operational2.9
Winscales Phase I and IIwind farm8.8operational2.9
Fairfield Farmwind farm7.8application withdrawn3.0
Winscales Moorwind farm6operational4.4
Weddicar Rigg Wind Farmwind farm12refused on appeal5.0
Oldside Wind Farmwind farm5.4operational7.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.6027, -3.5031).