Energy Projects Near You

Solar, wind and battery projects near Maryport (CA15)

25 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of CA15 (Cumberland): 2 are waiting for a planning decision, 8 approved but not yet running, 10 operational. The largest live scheme is Ewanrigg Farmhouse, Ewanrigg Solar Farm (13 MW solar farm, approved on 3 June 2026, not yet built), 1.1 km away. Offshore, 2 wind farms are recorded within 40 km; the nearest is Robin Rigg East (84 MW, operational), 14.9 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

25projects within 10 km
2awaiting a decision
8approved, not running
10operational

Projects within 10 km of CA15

Projects of 1 MW and more (17)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Ewanrigg Farmhouse, Ewanrigg Solar Farmsolar farmsolar farm13approved, not builtupdated Jun 2026Jun 2025granted Jun 2026Jun 2026Cumberland1.1
Land at Flimby Hall Farmwind farmwind farm6.2operationalupdated Jun 2013Jun 2009granted Jun 2010Jun 2013Cumberland3.5
Fleeter Wood Wind Farmwind farmwind farm10abandonedupdated Mar 2009Dec 2007granted Jan 2009Mar 2009Cumberland4.4
Wythegill Wind Turbinewind turbinewind turbine2.3operationalupdated Jun 2015Apr 2011granted Oct 2012Jun 2015Cumberland5.0
St Helen's Lanesolar farmsolar farm5operationalupdated May 2017Sep 2015granted Dec 2015May 2017Cumberland5.1
New Balance Athletic Shoes, Flimby To Maryportwind turbinewind turbine1approved, not builtupdated Sep 2024Mar 2023granted Jul 2024Sep 2024Cumberland5.2
New Balance Athletic Shoes, Flimby To Maryportwind turbinewind turbine1application withdrawnupdated Sep 2024Mar 2024—Sep 2024Cumberland5.2
Siddick Wind Farmwind farmwind farm4.2operationalupdated Oct 2011Apr 1995granted Dec 1995Oct 2011Cumberland5.8
Eastman Chemicals, Workingtonwind farmwind farm4operationalupdated Oct 2009Jun 2003granted Sep 2003Oct 2009Cumberland5.9
Former Broughton Lodge Resubmissionwind farmwind farm9refusedupdated Feb 2011Dec 2009—Feb 2011Cumberland6.4
Iggesund Wind Farmwind farmwind farm9refusedupdated Nov 2015Oct 2014refused Oct 2015Nov 2015Cumberland6.9
Oldside Wind Farmwind farmwind farm5.4operationalupdated Apr 2011Oct 1995granted Jan 1996Apr 2011Cumberland7.6
Tallentire Hillwind farmwind farm12operationalupdated Jun 2014Mar 2008granted Feb 2011Jun 2014Cumberland7.8
Winscales Moorwind farmwind farm6operationalupdated Dec 2017Oct 2006granted Jun 2007Dec 2017Cumberland7.8
Winscales Phase I and IIwind farmwind farm8.8operationalupdated Sep 2009Nov 1997granted Jun 1999Sep 2009Cumberland9.4
Chapel Banks, Curwen Roadrooftop solarrooftop solar3.2application submittedJun 2026——Cumberland9.4
Brownrigg Hall Wind Farmwind farmwind farm11.5refusedupdated Apr 2007Jul 2006refused Apr 2007Apr 2007Cumberland10.0
Smaller schemes under 1 MW, mostly rooftop solar (8)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Ewanrigg Farmhouse, Ewanriggbattery storagebattery storage—approved, not builtupdated Jun 2026Jun 2025granted Jun 2026Jun 2026Cumberland1.1
Netherhall Rugby Club -Micro Energy Storage Facilitybattery storagebattery storage0.2approved, not builtupdated Jun 2025Mar 2025granted May 2025Jun 2025Cumberland1.1
Maryport Sea Cadet Corpsrooftop solarrooftop solar—approved, not builtupdated May 2021Jan 2021granted Apr 2021May 2021Cumberland1.3
M-Sport Limitedsolar farmsolar farm0.2approved, not built may be out of dateupdated Jan 2022Feb 2021granted Apr 2021Jan 2022Cumberland5.5
M Sport, Dovenby Hall Estaterooftop solarrooftop solar0.8operationalupdated Oct 2023Jan 2023granted Feb 2023Oct 2023Cumberland6.1
Workington Leisure Centre, Griffin Street Solar Panlsrooftop solarrooftop solar0.2approved, not builtupdated Jan 2025Sep 2024granted Nov 2024Jan 2025Cumberland8.5
James Walker And Corooftop solarrooftop solar0.5approved, not builtupdated Mar 2022Mar 2022granted Apr 2022Mar 2022Cumberland8.7
Curwen Roadrooftop solarrooftop solar0.2application submitted may be out of dateupdated Mar 2022Mar 2022—Mar 2022Cumberland9.3

Distance from the average position of the CA15 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm3021013.2
Rooftop solar623104.1
Wind farm1100730
Wind turbine301101
Battery storage202000.2

MW in pipeline: pending, approved and under-construction capacity.

Offshore wind farms within 40 km

Wind farmMWStatus (REPD)km
Robin Rigg East84operationalupdated Aug 201714.9
Robin Rigg West90operationalupdated Aug 201716.4

Operational, approved and pending offshore wind farms; distance from the district centre to the REPD grid reference of each wind farm (one point per site, so the nearest turbines can be closer or further). All offshore wind farms in UK waters.

How Cumberland decides solar, wind and battery applications

ApplicationsCumberlandUK
Decided applications (solar, wind, battery)9110,236
Refused30 (33%)19%
Solar refused4 of 3212%
Onshore wind refused25 of 4545%
Battery storage refused1 of 1416%
Median time from submission to decision22.4 weeks17.0 weeks
Appeals lodged / allowed7 / 9—

All projects in Cumberland

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near CA15, 2 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.