Energy Projects Near You

Brownrigg Hall Wind Farm (11.5 MW)

Brownrigg Hall Wind Farm is an 11.5 MW wind farm project in Cumberland, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 5 April 2007; the record was last updated on 11 April 2007.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

11.5 MWwind farm
refusedstatus in REPD
11 April 2007record last updated
Cumberlandcouncil area

Planning timeline

DateStage
11 July 2006Application submitted
5 April 2007Refused by the planning authority

Project details

Technology
wind farm
Capacity
11.5 MW
Status (REPD)
refused
Record last updated
11 April 2007
Operator or applicant
Nuon Renewables
Planning authority
Cumberland
Planning application reference
not recorded
Turbines
5
Address (REPD)
Brownrigg Hall Edderside Cumbria
Council area (by location)
Cumberland
Time to decision
38 weeks
REPD reference
2933

Who decides

ApplicationsCumberlandUK
Decided applications (solar, wind, battery)9110,236
Refused30 (33%)19%
Solar refused4 of 3212%
Onshore wind refused25 of 4545%
Battery storage refused1 of 1416%
Median time from submission to decision22.4 weeks17.0 weeks
Appeals lodged / allowed7 / 9—

Other large projects within 10 km

ProjectTypeMWStatuskm
West Newtonsolar farm5refused0.7
Lancarrwind farm6.9application withdrawn2.2
Warwick Hallwind farm12refused2.5
Westnewtonwind farm6.2operational2.5
Westnewton (withdrawn)wind farm10application withdrawn2.5
West Farm, Aspatriabattery storage50approved, not built3.8
Aspatriasolar farm19operational4.0
Threapland Leeswind farm12application withdrawn7.1
Park Head Farmwind farm7.8refused8.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.783, -3.3854).