Energy Projects Near You

Aspatria (19 MW solar farm)

Aspatria is a 19 MW solar farm project in Cumberland, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 30 March 2015; the record was last updated on 4 October 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

19 MWsolar farm
operationalstatus in REPD
4 October 2016record last updated
Cumberlandcouncil area

Planning timeline

DateStage
2 July 2014Application submitted
18 November 2014Planning permission granted
1 December 2014Construction started
30 March 2015Operational

Project details

Technology
solar farm
Capacity
19 MW
Status (REPD)
operational
Record last updated
4 October 2016
Operator or applicant
United Photovoltaics
Planning authority
Cumberland
Planning application reference
2/2014/0468
Site area
32.1 ha
Address (REPD)
Pasture Farm, Westnewon Road, Aspatria, Wigton, Cumbria
Council area (by location)
Cumberland
Time to decision
20 weeks
REPD reference
2007

Who decides

ApplicationsCumberlandUK
Decided applications (solar, wind, battery)9110,236
Refused30 (33%)19%
Solar refused4 of 3212%
Onshore wind refused25 of 4545%
Battery storage refused1 of 1416%
Median time from submission to decision22.4 weeks17.0 weeks
Appeals lodged / allowed7 / 9—

Other large projects within 10 km

ProjectTypeMWStatuskm
Westnewtonwind farm6.2operational1.4
Warwick Hallwind farm12refused1.7
Westnewton (withdrawn)wind farm10application withdrawn1.8
West Farm, Aspatriabattery storage50approved, not built2.0
Lancarrwind farm6.9application withdrawn2.4
West Newtonsolar farm5refused3.3
Brownrigg Hall Wind Farmwind farm11.5refused4.0
Threapland Leeswind farm12application withdrawn4.4
Wharrels Hillsolar farm14.6appeal withdrawn6.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.778, -3.3241).