Westnewton (6.2 MW wind farm)

Westnewton is a 6.2 MW wind farm project in Cumberland, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 May 2014; the record was last updated on 21 July 2014.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

6.2 MWwind farm
operationalstatus in REPD
21 July 2014record last updated
Cumberlandcouncil area

Planning timeline

DateStage
24 December 2008Application submitted
2 July 2010Refused by the planning authority
4 February 2011Planning permission granted
4 February 2011Appeal allowed
17 September 2013Construction started
1 May 2014Operational

Project details

Technology
wind farm
Capacity
6.2 MW
Status (REPD)
operational
Record last updated
21 July 2014
Operator or applicant
Broadview Energy Limited
Planning authority
Cumberland
Planning application reference
2/2008/0997
Appeal reference
APP/GO908/A/10/2132949
Turbines
3
Address (REPD)
Warwick Hall Farm, Westnewton, Cumbria. CA7 3PF
Council area (by location)
Cumberland
Time to decision
110 weeks
REPD reference
4141

Who decides

ApplicationsCumberlandUK
Decided applications (solar, wind, battery)9110,236
Refused30 (33%)19%
Solar refused4 of 3212%
Onshore wind refused25 of 4545%
Battery storage refused1 of 1416%
Median time from submission to decision22.4 weeks17.0 weeks
Appeals lodged / allowed7 / 9—

Other large projects within 10 km

ProjectTypeMWStatuskm
Warwick Hallwind farm12refused0.6
Westnewton (withdrawn)wind farm10application withdrawn0.9
Lancarrwind farm6.9application withdrawn1.3
Aspatriasolar farm19operational1.4
West Newtonsolar farm5refused1.9
West Farm, Aspatriabattery storage50approved, not built2.0
Brownrigg Hall Wind Farmwind farm11.5refused2.5
Threapland Leeswind farm12application withdrawn5.2
Wharrels Hillsolar farm14.6appeal withdrawn7.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.7795, -3.3463).