Warwick Hall (12 MW wind farm)

Warwick Hall is a 12 MW wind farm project in Cumberland, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 13 July 2006; the record was last updated on 13 July 2006.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

12 MWwind farm
refusedstatus in REPD
13 July 2006record last updated
Cumberlandcouncil area

Planning timeline

DateStage
13 July 2006Refused by the planning authority

Project details

Technology
wind farm
Capacity
12 MW
Status (REPD)
refused
Record last updated
13 July 2006
Operator or applicant
Broadview Renewables
Planning authority
Cumberland
Planning application reference
not recorded
Turbines
6
Address (REPD)
Warwick Hall Winscales
Council area (by location)
Cumberland
REPD reference
2961

Who decides

ApplicationsCumberlandUK
Decided applications (solar, wind, battery)9110,236
Refused30 (33%)19%
Solar refused4 of 3212%
Onshore wind refused25 of 4545%
Battery storage refused1 of 1416%
Median time from submission to decision22.4 weeks17.0 weeks
Appeals lodged / allowed7 / 9—

Other large projects within 10 km

ProjectTypeMWStatuskm
Westnewtonwind farm6.2operational0.6
Lancarrwind farm6.9application withdrawn0.8
Westnewton (withdrawn)wind farm10application withdrawn1.5
West Farm, Aspatriabattery storage50approved, not built1.6
Aspatriasolar farm19operational1.7
West Newtonsolar farm5refused1.9
Brownrigg Hall Wind Farmwind farm11.5refused2.5
Threapland Leeswind farm12application withdrawn4.8
Wharrels Hillsolar farm14.6appeal withdrawn6.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.7743, -3.3499).