West Farm, Aspatria (50 MW battery storage)

West Farm, Aspatria is a 50 MW battery storage project in Cumberland, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 4 September 2024, not yet built; the record was last updated on 10 July 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

50 MWbattery storage
approved, not builtstatus in REPD
10 July 2025record last updated
Cumberlandcouncil area

Planning timeline

DateStage
22 April 2024Application submitted
4 September 2024Planning permission granted

Project details

Technology
battery storage (stand-alone storage)
Capacity
50 MW
Status (REPD)
approved, not built
Record last updated
10 July 2025
Operator or applicant
Net Zero Seventeen Limited
Planning authority
Cumberland
Planning application reference
FUL/2024/0085
Address (REPD)
West Farm, West Street, Aspatria, Wigton
Council area (by location)
Cumberland
Time to decision
19 weeks
Name in REPD
West Farm, Aspatria - Battery Storage Facility
REPD reference
15673

Who decides

ApplicationsCumberlandUK
Decided applications (solar, wind, battery)9110,236
Refused30 (33%)19%
Solar refused4 of 3212%
Onshore wind refused25 of 4545%
Battery storage refused1 of 1416%
Median time from submission to decision22.4 weeks17.0 weeks
Appeals lodged / allowed7 / 9—

Other large projects within 10 km

ProjectTypeMWStatuskm
Warwick Hallwind farm12refused1.6
Lancarrwind farm6.9application withdrawn1.7
Aspatriasolar farm19operational2.0
Westnewtonwind farm6.2operational2.0
Westnewton (withdrawn)wind farm10application withdrawn2.9
Threapland Leeswind farm12application withdrawn3.3
West Newtonsolar farm5refused3.4
Brownrigg Hall Wind Farmwind farm11.5refused3.8
Wharrels Hillsolar farm14.6appeal withdrawn5.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.7621, -3.3381).