Energy Projects Near You

Solar, wind and battery projects near Wigton (CA7)

19 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of CA7 (Cumberland): 2 are waiting for a planning decision, 3 approved but not yet running, 5 operational. The largest live scheme is West Farm, Aspatria (50 MW battery storage, approved on 4 September 2024, not yet built), 8.1 km away. Offshore, 2 wind farms are recorded within 40 km; the nearest is Robin Rigg East (84 MW, operational), 29.7 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

19projects within 10 km
2awaiting a decision
3approved, not running
5operational

Projects within 10 km of CA7

Projects of 1 MW and more (15)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
High Pow Farmwind farmwind farm3.9operationalupdated Jul 2012Jul 2004granted Oct 2004Jul 2012Cumberland3.7
High Pow Extensionwind farmwind farm16application withdrawnupdated Dec 2013Jul 2013—Dec 2013Cumberland5.1
Aspatriasolar farmsolar farm19operationalupdated Oct 2016Jul 2014granted Nov 2014Oct 2016Cumberland6.4
Westnewton (withdrawn)wind farmwind farm10application withdrawnupdated Mar 2009Sep 2007—Mar 2009Cumberland7.2
Westnewtonwind farmwind farm6.2operationalupdated Jul 2014Dec 2008granted Feb 2011Jul 2014Cumberland7.6
Warwick Hallwind farmwind farm12refusedupdated Jul 2006—refused Jul 2006Jul 2006Cumberland8.0
West Farm, Aspatriabattery storagebattery storage50approved, not builtupdated Jul 2025Apr 2024granted Sep 2024Jul 2025Cumberland8.1
Threapland Leeswind farmwind farm12application withdrawnupdated Oct 2011Oct 2009—Oct 2011Cumberland8.6
Hellrigg Wind farmwind farmwind farm9.2operationalupdated Mar 2012Jan 2007granted Dec 2007Mar 2012Cumberland8.6
Park Head Farmwind farmwind farm7.8refusedupdated Nov 2005Jun 2004refused Oct 2004Nov 2005Cumberland8.6
Wharrels Hillsolar farmsolar farm14.6appeal withdrawnupdated Aug 2018Aug 2014refused Jul 2015Aug 2018Cumberland8.7
Lancarrwind farmwind farm6.9application withdrawnupdated Nov 2015Jan 2015—Nov 2015Cumberland8.8
West Newtonsolar farmsolar farm5refusedupdated Nov 2015Oct 2015refused Mar 2016Nov 2015Cumberland9.1
Wharrels Hill Wind Farmwind farmwind farm10.4operationalupdated May 2009Dec 2000granted Jun 2002May 2009Cumberland9.7
Brownrigg Hall Wind Farmwind farmwind farm11.5refusedupdated Apr 2007Jul 2006refused Apr 2007Apr 2007Cumberland9.8
Smaller schemes under 1 MW, mostly rooftop solar (4)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Pow Motey, Langrigg Solar Panels & Batteries Storagerooftop solarrooftop solar0.2approved, not builtupdated May 2022May 2022granted Jun 2022May 2022Cumberland4.0
Pow Motey, Langrigg Solar Panels & Batteries Storagebattery storagebattery storage—application submitted may be out of dateupdated May 2022May 2022—May 2022Cumberland4.0
Tarns Farm, Sillothwind turbinewind turbine0.2application submittedupdated Mar 2026Feb 2026—Mar 2026Cumberland8.6
Brocklebank, Reathwaite Farmrooftop solarrooftop solar0.7approved, not builtupdated May 2024Feb 2024granted Apr 2024May 2024Cumberland9.9

Distance from the average position of the CA7 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm300110
Rooftop solar202000.9
Wind farm1100430
Wind turbine110000.2
Battery storage2110050

MW in pipeline: pending, approved and under-construction capacity.

Offshore wind farms within 40 km

Wind farmMWStatus (REPD)km
Robin Rigg East84operationalupdated Aug 201729.7
Robin Rigg West90operationalupdated Aug 201732.1

Operational, approved and pending offshore wind farms; distance from the district centre to the REPD grid reference of each wind farm (one point per site, so the nearest turbines can be closer or further). All offshore wind farms in UK waters.

How Cumberland decides solar, wind and battery applications

ApplicationsCumberlandUK
Decided applications (solar, wind, battery)9110,236
Refused30 (33%)19%
Solar refused4 of 3212%
Onshore wind refused25 of 4545%
Battery storage refused1 of 1416%
Median time from submission to decision22.4 weeks17.0 weeks
Appeals lodged / allowed7 / 9—

All projects in Cumberland

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near CA7, 1 project has a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.