Energy Projects Near You

Lancarr (6.9 MW wind farm)

Lancarr is a 6.9 MW wind farm project in Cumberland, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application withdrawn on 7 October 2015; the record was last updated on 5 November 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

6.9 MWwind farm
application withdrawnstatus in REPD
5 November 2015record last updated
Cumberlandcouncil area

Planning timeline

DateStage
15 January 2015Application submitted
7 October 2015Application withdrawn

Project details

Technology
wind farm
Capacity
6.9 MW
Status (REPD)
application withdrawn
Record last updated
5 November 2015
Operator or applicant
Airvolution Energy
Planning authority
Cumberland
Planning application reference
2/2015/0030
Turbines
3
Turbine height
110 m
Address (REPD)
Land at Whitelees Farm, Aiglegill Farm and West Farm, Nr. Aspatria
Council area (by location)
Cumberland
REPD reference
4958

Who decides

ApplicationsCumberlandUK
Decided applications (solar, wind, battery)9110,236
Refused30 (33%)19%
Solar refused4 of 3212%
Onshore wind refused25 of 4545%
Battery storage refused1 of 1416%
Median time from submission to decision22.4 weeks17.0 weeks
Appeals lodged / allowed7 / 9—

Other large projects within 10 km

ProjectTypeMWStatuskm
Warwick Hallwind farm12refused0.8
Westnewtonwind farm6.2operational1.3
West Farm, Aspatriabattery storage50approved, not built1.7
West Newtonsolar farm5refused1.8
Westnewton (withdrawn)wind farm10application withdrawn2.1
Brownrigg Hall Wind Farmwind farm11.5refused2.2
Aspatriasolar farm19operational2.4
Threapland Leeswind farm12application withdrawn4.9
Wharrels Hillsolar farm14.6appeal withdrawn7.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.7704, -3.3598).