High Pow Extension (16 MW wind farm)

High Pow Extension is a 16 MW wind farm project in Cumberland, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application withdrawn on 23 December 2013; the record was last updated on 24 December 2013.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

16 MWwind farm
application withdrawnstatus in REPD
24 December 2013record last updated
Cumberlandcouncil area

Planning timeline

DateStage
12 July 2013Application submitted
23 December 2013Application withdrawn

Project details

Technology
wind farm
Capacity
16 MW
Status (REPD)
application withdrawn
Record last updated
24 December 2013
Operator or applicant
REG Windpower
Planning authority
Cumberland
Planning application reference
2/2013/0519
Turbines
8
Address (REPD)
Percy Hill, Boltongate, Wigton, Cumbria
Council area (by location)
Cumberland
REPD reference
3324

Who decides

ApplicationsCumberlandUK
Decided applications (solar, wind, battery)9110,236
Refused30 (33%)19%
Solar refused4 of 3212%
Onshore wind refused25 of 4545%
Battery storage refused1 of 1416%
Median time from submission to decision22.4 weeks17.0 weeks
Appeals lodged / allowed7 / 9—

Other large projects within 10 km

ProjectTypeMWStatuskm
Hilltop Wind Farmwind farm8.8refused5.5
Wharrels Hillsolar farm14.6appeal withdrawn7.9
Wharrels Hill Wind Farmwind farm10.4operational8.5
Carwath Wind Farmwind farm7.5refused9.0
Threapland Leeswind farm12application withdrawn9.0
Aspatriasolar farm19operational9.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.7769, -3.1796).