Energy Projects Near You

Hilltop Wind Farm (8.8 MW)

Hilltop Wind Farm is an 8.8 MW wind farm project in Cumberland, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 5 July 2000; the record was last updated on 30 October 2011.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

8.8 MWwind farm
refusedstatus in REPD
30 October 2011record last updated
Cumberlandcouncil area

Planning timeline

DateStage
22 June 1999Application submitted
5 July 2000Refused by the planning authority

Project details

Technology
wind farm
Capacity
8.8 MW
Status (REPD)
refused
Record last updated
30 October 2011
Operator or applicant
Cumbria Wind Farms
Planning authority
Cumberland
Planning application reference
not recorded
Address (REPD)
Hilltop Farm Brocklebank Westward Wigton Cumbria
Council area (by location)
Cumberland
Time to decision
54 weeks
REPD reference
3490

Who decides

ApplicationsCumberlandUK
Decided applications (solar, wind, battery)9110,236
Refused30 (33%)19%
Solar refused4 of 3212%
Onshore wind refused25 of 4545%
Battery storage refused1 of 1416%
Median time from submission to decision22.4 weeks17.0 weeks
Appeals lodged / allowed7 / 9—

Other large projects within 10 km

ProjectTypeMWStatuskm
High Pow Extensionwind farm16application withdrawn5.5
Carwath Wind Farmwind farm7.5refused6.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.7635, -3.0972).