Wharrels Hill Wind Farm (10.4 MW)

Wharrels Hill Wind Farm is a 10.4 MW wind farm project in Cumberland, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 7 August 2007; the record was last updated on 6 May 2009.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

10.4 MWwind farm
operationalstatus in REPD
6 May 2009record last updated
Cumberlandcouncil area

Planning timeline

DateStage
23 December 2000Application submitted
19 June 2002Planning permission granted
1 April 2007Construction started
7 August 2007Operational

Project details

Technology
wind farm
Capacity
10.4 MW
Status (REPD)
operational
Record last updated
6 May 2009
Operator or applicant
Wharrels Hill Windfarm Ltd/ National Windpower
Planning authority
Cumberland
Planning application reference
2/2001/0008
Appeal reference
APP/G0908/A/01/1075972
Turbines
8
Address (REPD)
Wharrels Hill Bothel Cumbria
Council area (by location)
Cumberland
Time to decision
78 weeks
REPD reference
2618

Who decides

ApplicationsCumberlandUK
Decided applications (solar, wind, battery)9110,236
Refused30 (33%)19%
Solar refused4 of 3212%
Onshore wind refused25 of 4545%
Battery storage refused1 of 1416%
Median time from submission to decision22.4 weeks17.0 weeks
Appeals lodged / allowed7 / 9—

Other large projects within 10 km

ProjectTypeMWStatuskm
Wharrels Hillsolar farm14.6appeal withdrawn1.0
Threapland Leeswind farm12application withdrawn2.7
Tallentire Hillwind farm12operational5.7
West Farm, Aspatriabattery storage50approved, not built6.0
Aspatriasolar farm19operational6.9
Warwick Hallwind farm12refused7.5
Lancarrwind farm6.9application withdrawn7.6
Westnewtonwind farm6.2operational7.8
High Pow Extensionwind farm16application withdrawn8.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.7231, -3.2746).