Energy Projects Near You

Hellrigg Wind farm (9.2 MW)

Hellrigg Wind farm is a 9.2 MW wind farm project in Cumberland, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 14 September 2011; the record was last updated on 15 March 2012.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

9.2 MWwind farm
operationalstatus in REPD
15 March 2012record last updated
Cumberlandcouncil area

Planning timeline

DateStage
29 January 2007Application submitted
11 December 2007Planning permission granted
1 May 2011Construction started
14 September 2011Operational

Project details

Technology
wind farm
Capacity
9.2 MW
Status (REPD)
operational
Record last updated
15 March 2012
Operator or applicant
Npower Renewables
Planning authority
Cumberland
Planning application reference
2/2007/0076
Turbines
4
Address (REPD)
Park Head Farm Silloth Carlisle
Council area (by location)
Cumberland
Time to decision
45 weeks
REPD reference
3002

Earlier applications for this site

ApplicationMWSubmittedOutcome
Hellrigg Wind Farm 2/2004/08437.825 June 2004refused 7 October 2004

Who decides

ApplicationsCumberlandUK
Decided applications (solar, wind, battery)9110,236
Refused30 (33%)19%
Solar refused4 of 3212%
Onshore wind refused25 of 4545%
Battery storage refused1 of 1416%
Median time from submission to decision22.4 weeks17.0 weeks
Appeals lodged / allowed7 / 9—

Other large projects within 10 km

ProjectTypeMWStatuskm
Park Head Farmwind farm7.8refused0.1
Westnewton (withdrawn)wind farm10application withdrawn7.3
West Newtonsolar farm5refused7.9
Brownrigg Hall Wind Farmwind farm11.5refused8.2
Westnewtonwind farm6.2operational8.2
Aspatriasolar farm19operational8.5
Warwick Hallwind farm12refused8.8
Lancarrwind farm6.9application withdrawn9.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.8533, -3.3475).