Iggesund Wind Farm (9 MW)
Iggesund Wind Farm is a 9 MW wind farm project in Cumberland, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 8 October 2015; the record was last updated on 5 November 2015.
9 MWwind farm
refusedstatus in REPD
5 November 2015record last updated
Cumberlandcouncil area
Planning timeline
| Date | Stage |
|---|---|
| 8 October 2014 | Application submitted |
| 8 October 2015 | Refused by the planning authority |
Project details
- Technology
- wind farm
- Capacity
- 9 MW
- Status (REPD)
- refused
- Record last updated
- 5 November 2015
- Operator or applicant
- Iggesund Paperboard
- Planning authority
- Cumberland
- Planning application reference
- 2/2014/0737
- Turbines
- 3
- Turbine height
- 110 m
- Address (REPD)
- Iggesund Paperboard (Workington) Ltd, Siddick, Workington
- Council area (by location)
- Cumberland
- Time to decision
- 52 weeks
- REPD reference
- 4719
Who decides
| Applications | Cumberland | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 91 | 10,236 |
| Refused | 30 (33%) | 19% |
| Solar refused | 4 of 32 | 12% |
| Onshore wind refused | 25 of 45 | 45% |
| Battery storage refused | 1 of 14 | 16% |
| Median time from submission to decision | 22.4 weeks | 17.0 weeks |
| Appeals lodged / allowed | 7 / 9 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Oldside Wind Farm | wind farm | 5.4 | operational | 0.8 |
| St Helen's Lane | solar farm | 5 | operational | 1.8 |
| Land at Flimby Hall Farm | wind farm | 6.2 | operational | 3.4 |
| Winscales Moor | wind farm | 6 | operational | 3.9 |
| Winscales Phase I and II | wind farm | 8.8 | operational | 4.6 |
| Moorhouse Farm | solar farm | 5 | operational | 5.5 |
| Ewanrigg Farmhouse, Ewanrigg Solar Farm | solar farm | 13 | approved, not built | 5.8 |
| Lillyhall Wind Farm | wind farm | 9.2 | refused | 6.3 |
| Potato Pot Wind Farm | wind farm | 6 | operational | 7.2 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.663, -3.5455).