Solar, wind and battery projects near Kirkcudbright (DG6)
9 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of DG6 (Dumfries and Galloway): 5 approved but not yet running. The largest live scheme is High Nunton Farm Solar Farm & Battery Storage (49.9 MW solar farm, approved on 22 January 2025, not yet built), 3.5 km away. Offshore, 2 wind farms are recorded within 40 km; the nearest is Robin Rigg West (90 MW, operational), 23.2 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of DG6
Projects of 1 MW and more (7)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Solar Park & Battery Storage at Little Drum Near High Banksbattery storage | battery storage | 12 | approved, not builtupdated Feb 2026 | Jan 2025 | granted Jul 2025 | Feb 2026 | Dumfries and Galloway | 2.8 |
| Solar Park & Battery Storage at Little Drum Near High Bankssolar farm | solar farm | 36 | approved, not builtupdated Feb 2026 | Jan 2025 | granted Jul 2025 | Feb 2026 | Dumfries and Galloway | 3.0 |
| High Nunton Farm Solar Farm & Battery Storagesolar farm | solar farm | 49.9 | approved, not builtupdated Jun 2026 | Jan 2022 | granted Jan 2025 | Jun 2026 | Dumfries and Galloway | 3.5 |
| Chapmans Howe Wind Farmwind farm | wind farm | 6.9 | refused on appealupdated Jan 2015 | Jun 2013 | refused Jan 2015 | Jan 2015 | Dumfries and Galloway | 6.1 |
| Mayfield Community Wind Farmwind farm | wind farm | 20.4 | refused on appealupdated Sep 2014 | Dec 2011 | refused Dec 2012 | Sep 2014 | Dumfries and Galloway | 6.5 |
| Barcloy Hill Wind Farmwind farm | wind farm | 12.5 | refused on appealupdated Jul 2015 | Dec 2012 | refused Jul 2014 | Jul 2015 | Dumfries and Galloway | 6.5 |
| Knockendurrick Wind Farmwind farm | wind farm | 14 | refusedupdated Sep 2018 | Oct 2013 | refused Aug 2018 | Sep 2018 | Dumfries and Galloway | 7.6 |
Smaller schemes under 1 MW, mostly rooftop solar (2)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| High Nunton Farm Solar Farm & Battery Storagebattery storage | battery storage | — | approved, not builtupdated Jun 2026 | Jan 2022 | granted Jan 2025 | Jun 2026 | Dumfries and Galloway | 3.5 |
| Rerrick Park Farm, Dundrennan Wind Turbine & Substationwind turbine | wind turbine | 0.2 | approved, not builtupdated May 2026 | Nov 2025 | granted Mar 2026 | May 2026 | Dumfries and Galloway | 9.0 |
Distance from the average position of the DG6 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 2 | 0 | 2 | 0 | 0 | 85.9 |
| Wind farm | 4 | 0 | 0 | 0 | 4 | 0 |
| Wind turbine | 1 | 0 | 1 | 0 | 0 | 0.2 |
| Battery storage | 2 | 0 | 2 | 0 | 0 | 12 |
MW in pipeline: pending, approved and under-construction capacity.
Offshore wind farms within 40 km
| Wind farm | MW | Status (REPD) | km |
|---|---|---|---|
| Robin Rigg West | 90 | operationalupdated Aug 2017 | 23.2 |
| Robin Rigg East | 84 | operationalupdated Aug 2017 | 24.5 |
Operational, approved and pending offshore wind farms; distance from the district centre to the REPD grid reference of each wind farm (one point per site, so the nearest turbines can be closer or further). All offshore wind farms in UK waters.
How Dumfries and Galloway decides solar, wind and battery applications
| Applications | Dumfries and Galloway | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 106 | 10,236 |
| Refused | 40 (38%) | 19% |
| Solar refused | 1 of 18 | 12% |
| Onshore wind refused | 33 of 72 | 45% |
| Battery storage refused | 6 of 16 | 16% |
| Median time from submission to decision | 60.9 weeks | 17.0 weeks |
| Appeals lodged / allowed | 19 / 17 | — |
All projects in Dumfries and Galloway
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.