Energy Projects Near You

Solar, wind and battery projects near Dalbeattie (DG5)

6 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of DG5 (Dumfries and Galloway): 3 approved but not yet running, 1 operational. The largest live scheme is Plascow Farm (0.5 MW solar farm, approved on 8 February 2024, not yet built), 6.1 km away. Offshore, 2 wind farms are recorded within 40 km; the nearest is Robin Rigg East (84 MW, operational), 19.0 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

6projects within 10 km
0awaiting a decision
3approved, not running
1operational

Projects within 10 km of DG5

Projects of 1 MW and more (2)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Plascow wind clusterwind farmwind farm2.4operationalupdated Mar 2016May 2013granted Mar 2014Mar 2016Dumfries and Galloway5.1
Doon Hill Windfarmwind farmwind farm4.9refused on appealupdated Sep 2014Jan 2007refused Feb 2007Sep 2014Dumfries and Galloway6.5
Smaller schemes under 1 MW, mostly rooftop solar (4)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Unit 4, Industrial Siterooftop solarrooftop solar0.2approved, not builtupdated Mar 2024Jan 2024granted Feb 2024Mar 2024Dumfries and Galloway0.6
Torkirra, Kirkgunzeonwind turbinewind turbine—refusedupdated Mar 2025Oct 2024refused Mar 2025Mar 2025Dumfries and Galloway5.4
Plascow Wind Turbinewind farmwind farm—approved, not builtupdated Jun 2023Dec 2020granted Nov 2021Jun 2023Dumfries and Galloway5.5
Plascow Farmsolar farmsolar farm0.5approved, not builtupdated Feb 2024Nov 2023granted Feb 2024Feb 2024Dumfries and Galloway6.1

Distance from the average position of the DG5 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm101000.5
Rooftop solar101000.2
Wind farm301110
Wind turbine100010

MW in pipeline: pending, approved and under-construction capacity.

Offshore wind farms within 40 km

Wind farmMWStatus (REPD)km
Robin Rigg East84operationalupdated Aug 201719.0
Robin Rigg West90operationalupdated Aug 201720.1

Operational, approved and pending offshore wind farms; distance from the district centre to the REPD grid reference of each wind farm (one point per site, so the nearest turbines can be closer or further). All offshore wind farms in UK waters.

How Dumfries and Galloway decides solar, wind and battery applications

ApplicationsDumfries and GallowayUK
Decided applications (solar, wind, battery)10610,236
Refused40 (38%)19%
Solar refused1 of 1812%
Onshore wind refused33 of 7245%
Battery storage refused6 of 1616%
Median time from submission to decision60.9 weeks17.0 weeks
Appeals lodged / allowed19 / 17—

All projects in Dumfries and Galloway

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.