Energy Projects Near You

Solar, wind and battery projects near Thornhill (DG3)

2 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of DG3 (Dumfries and Galloway): none of them is pending, approved or operational. The largest scheme is Auchencairn Forest (32 MW wind farm, application withdrawn on 8 May 2015), 9.8 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

2projects within 10 km
0awaiting a decision
0approved, not running
0operational

Projects within 10 km of DG3

Projects of 1 MW and more (2)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Blackwood Wind Farmwind farmwind farm10.3refused on appealupdated Oct 2016Feb 2012refused May 2016Oct 2016Dumfries and Galloway9.8
Auchencairn Forestwind farmwind farm32application withdrawnupdated May 2015Sep 2011—May 2015Dumfries and Galloway9.8

Distance from the average position of the DG3 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Wind farm200010

MW in pipeline: pending, approved and under-construction capacity.

How Dumfries and Galloway decides solar, wind and battery applications

ApplicationsDumfries and GallowayUK
Decided applications (solar, wind, battery)10610,236
Refused40 (38%)19%
Solar refused1 of 1812%
Onshore wind refused33 of 7245%
Battery storage refused6 of 1616%
Median time from submission to decision60.9 weeks17.0 weeks
Appeals lodged / allowed19 / 17—

All projects in Dumfries and Galloway

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.