Energy Projects Near You

Auchencairn Forest (32 MW wind farm)

Auchencairn Forest is a 32 MW wind farm project in Dumfries and Galloway, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application withdrawn on 8 May 2015; the record was last updated on 28 May 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

32 MWwind farm
application withdrawnstatus in REPD
28 May 2015record last updated
Dumfries and Gallowaycouncil area

Planning timeline

DateStage
12 September 2011Application submitted
8 May 2015Application withdrawn

Project details

Technology
wind farm
Capacity
32 MW
Status (REPD)
application withdrawn
Record last updated
28 May 2015
Operator or applicant
Acciona Energy
Planning authority
Dumfries and Galloway
Planning application reference
11/P/3/0397
Turbines
16
Address (REPD)
Closeburn, Thornhill, Dumfries & Galloway
Council area (by location)
Dumfries and Galloway
REPD reference
4547

Who decides

ApplicationsDumfries and GallowayUK
Decided applications (solar, wind, battery)10610,236
Refused40 (38%)19%
Solar refused1 of 1812%
Onshore wind refused33 of 7245%
Battery storage refused6 of 1616%
Median time from submission to decision60.9 weeks17.0 weeks
Appeals lodged / allowed19 / 17—

Other large projects within 10 km

ProjectTypeMWStatuskm
Dalswintonwind farm30operational3.5
Harestaneswind farm136operational5.4
Blackwood Wind Farmwind farm10.3refused on appeal6.1
Harestanes Windfarmbattery storage100under construction7.8
Harestanes West Windfarmwind farm84application submitted9.3
Minnygapwind farm25operational9.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.2152, -3.6493).