Dalswinton (30 MW wind farm)

Dalswinton is a 30 MW wind farm project in Dumfries and Galloway, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 15 March 2008; the record was last updated on 25 September 2014.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

30 MWwind farm
operationalstatus in REPD
25 September 2014record last updated
Dumfries and Gallowaycouncil area

Planning timeline

DateStage
13 October 2003Application submitted
20 January 2005Planning permission granted
1 April 2007Construction started
15 March 2008Operational

Project details

Technology
wind farm
Capacity
30 MW
Status (REPD)
operational
Record last updated
25 September 2014
Operator or applicant
Airtricity Scotland
Planning authority
Dumfries and Galloway
Planning application reference
03P30610
Turbines
15
Address (REPD)
Nr village of Dalswinton Dumfries
Council area (by location)
Dumfries and Galloway
Time to decision
66 weeks
REPD reference
4520

Who decides

ApplicationsDumfries and GallowayUK
Decided applications (solar, wind, battery)10610,236
Refused40 (38%)19%
Solar refused1 of 1812%
Onshore wind refused33 of 7245%
Battery storage refused6 of 1616%
Median time from submission to decision60.9 weeks17.0 weeks
Appeals lodged / allowed19 / 17—

Other large projects within 10 km

ProjectTypeMWStatuskm
Auchencairn Forestwind farm32application withdrawn3.5
Blackwood Wind Farmwind farm10.3refused on appeal3.7
Harestaneswind farm136operational7.8
Harestanes West Windfarmwind farm84application submitted9.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.1841, -3.6506).