Blackwood Wind Farm (10.3 MW)

Blackwood Wind Farm is a 10.3 MW wind farm project in Dumfries and Galloway, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 26 August 2016; the record was last updated on 4 October 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

10.3 MWwind farm
refused on appealstatus in REPD
4 October 2016record last updated
Dumfries and Gallowaycouncil area

Planning timeline

DateStage
14 February 2012Application submitted
26 May 2016Refused by the planning authority
26 August 2016Appeal lodged
26 August 2016Appeal refused

Project details

Technology
wind farm
Capacity
10.3 MW
Status (REPD)
refused on appeal
Record last updated
4 October 2016
Operator or applicant
Force 9 Energy
Planning authority
Dumfries and Galloway
Planning application reference
12/P/3/0060
Appeal reference
PPA-170-2118
Turbines
5
Address (REPD)
LAND TO EAST OF BLACKCRAIG HILL, HIGH AULDGIRTH, DUMFRIES
Council area (by location)
Dumfries and Galloway
Time to decision
223 weeks
REPD reference
4453

Who decides

ApplicationsDumfries and GallowayUK
Decided applications (solar, wind, battery)10610,236
Refused40 (38%)19%
Solar refused1 of 1812%
Onshore wind refused33 of 7245%
Battery storage refused6 of 1616%
Median time from submission to decision60.9 weeks17.0 weeks
Appeals lodged / allowed19 / 17—

Other large projects within 10 km

ProjectTypeMWStatuskm
Dalswintonwind farm30operational3.7
Auchencairn Forestwind farm32application withdrawn6.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.169, -3.7021).