Energy Projects Near You

Solar, wind and battery projects near Moffat (DG10)

10 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of DG10 (Dumfries and Galloway): 2 are waiting for a planning decision, 4 approved but not yet running, 1 operational. The largest live scheme is Daer Wind Farm (100 MW wind farm, application submitted on 26 May 2021, no decision recorded; REPD status may be out of date), 9.0 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

10projects within 10 km
2awaiting a decision
4approved, not running
1operational

Projects within 10 km of DG10

Projects of 1 MW and more (10)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
East Kilbridebattery storagebattery storage49.9under constructionupdated Aug 2024Mar 2022granted Aug 2022Aug 2024Dumfries and Galloway1.5
Milton Farmbattery storagebattery storage49.9approved, not builtupdated Aug 2025Jul 2024granted Jul 2025Aug 2025Dumfries and Galloway2.6
Milton Farmbattery storagebattery storage49.9approved, not builtupdated Aug 2025Jul 2024granted Jul 2025Aug 2025Dumfries and Galloway2.6
Scoop Hill Wind Farmwind farmwind farm432refusedupdated Jun 2026Nov 2020refused Feb 2026Jun 2026Dumfries and Galloway8.6
Scoop Hill Wind Farmbattery storagebattery storage200refusedNov 2020refused Feb 2026—Dumfries and Galloway8.6
Harestanes Wind Farm Extensionwind farmwind farm14refusedupdated Apr 2016Nov 2013refused Dec 2015Apr 2016Dumfries and Galloway8.7
Daer Wind Farmwind farmwind farm100application submitted may be out of dateupdated Mar 2019May 2021—Mar 2019Dumfries and Galloway9.0
Daer Wind Farmbattery storagebattery storage100application submitted may be out of dateupdated Jun 2021May 2021—Jun 2021Dumfries and Galloway9.0
Minnygapwind farmwind farm25operationalupdated May 2017Jun 2009granted Jun 2014May 2017Dumfries and Galloway9.3
Harestanes Windfarmbattery storagebattery storage100under constructionupdated Jul 2024Jun 2019granted Dec 2019Jul 2024Dumfries and Galloway9.9

Distance from the average position of the DG10 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Wind farm41012100
Battery storage61401350

MW in pipeline: pending, approved and under-construction capacity.

How Dumfries and Galloway decides solar, wind and battery applications

ApplicationsDumfries and GallowayUK
Decided applications (solar, wind, battery)10610,236
Refused40 (38%)19%
Solar refused1 of 1812%
Onshore wind refused33 of 7245%
Battery storage refused6 of 1616%
Median time from submission to decision60.9 weeks17.0 weeks
Appeals lodged / allowed19 / 17—

All projects in Dumfries and Galloway

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near DG10, 2 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.