Energy Projects Near You

Milton Farm (49.9 MW battery storage, REPD 13846)

Milton Farm is a 49.9 MW battery storage project in Dumfries and Galloway, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 30 July 2025, not yet built; the record was last updated on 19 August 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWbattery storage
approved, not builtstatus in REPD
19 August 2025record last updated
Dumfries and Gallowaycouncil area

Planning timeline

DateStage
10 July 2024Application submitted
30 July 2025Planning permission granted
30 July 2030Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
49.9 MW
Status (REPD)
approved, not built
Record last updated
19 August 2025
Operator or applicant
Renewco Power
Planning authority
Dumfries and Galloway
Planning application reference
24/1264/FUL
Address (REPD)
Milton Farm, Moffat
Council area (by location)
Dumfries and Galloway
Time to decision
55 weeks
Name in REPD
Milton Farm - Energy Storage System
REPD reference
13846

Who decides

ApplicationsDumfries and GallowayUK
Decided applications (solar, wind, battery)10610,236
Refused40 (38%)19%
Solar refused1 of 1812%
Onshore wind refused33 of 7245%
Battery storage refused6 of 1616%
Median time from submission to decision60.9 weeks17.0 weeks
Appeals lodged / allowed19 / 17—

Other large projects within 10 km

ProjectTypeMWStatuskm
Milton Farmbattery storage49.9approved, not built<0.1
East Kilbridebattery storage49.9under construction4.1
Scoop Hill Wind Farmwind farm432refused6.6
Minnygapwind farm25operational7.8
Harestanes Wind Farm Extensionwind farm14refused9.3
Harestanes Windfarmbattery storage100under construction9.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.2977, -3.4265).