East Kilbride (49.9 MW battery storage)

East Kilbride is a 49.9 MW battery storage project in Dumfries and Galloway, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: under construction since 1 May 2024; the record was last updated on 23 August 2024.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWbattery storage
under constructionstatus in REPD
23 August 2024record last updated
Dumfries and Gallowaycouncil area

Planning timeline

DateStage
28 March 2022Application submitted
22 August 2022Planning permission granted
1 May 2024Construction started

Project details

Technology
battery storage (stand-alone storage)
Capacity
49.9 MW
Status (REPD)
under construction
Record last updated
23 August 2024
Operator or applicant
Engie Regeneration Limited
Planning authority
South Lanarkshire
Planning application reference
P/22/0472
Address (REPD)
North E/O East Kilbride, 275kv Grid Substation, Cairnmuir Road, East Kilbride, Moffat
Council area (by location)
Dumfries and Galloway
Time to decision
21 weeks
Name in REPD
East Kilbride - Battery storage
REPD reference
9013

Who decides

ApplicationsSouth LanarkshireUK
Decided applications (solar, wind, battery)8910,236
Refused30 (34%)19%
Solar refused2 of 2012%
Onshore wind refused21 of 5645%
Battery storage refused7 of 1316%
Median time from submission to decision47.4 weeks17.0 weeks
Appeals lodged / allowed6 / 5—

Other large projects within 10 km

ProjectTypeMWStatuskm
Milton Farmbattery storage49.9approved, not built4.1
Milton Farmbattery storage49.9approved, not built4.1
Daer Wind Farmwind farm100application submitted8.5
Harestanes Wind Farm Extensionwind farm14refused8.8
Earlshaugh Wind Farmwind farm55.2abandoned9.2
Scoop Hill Wind Farmwind farm432refused9.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.3336, -3.4443).