Energy Projects Near You

Chapmans Howe Wind Farm (6.9 MW)

Chapmans Howe Wind Farm is a 6.9 MW wind farm project in Dumfries and Galloway, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 12 January 2015; the record was last updated on 26 January 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

6.9 MWwind farm
refused on appealstatus in REPD
26 January 2015record last updated
Dumfries and Gallowaycouncil area

Planning timeline

DateStage
28 June 2013Application submitted
28 August 2014Appeal lodged
12 January 2015Refused by the planning authority
12 January 2015Appeal refused

Project details

Technology
wind farm
Capacity
6.9 MW
Status (REPD)
refused on appeal
Record last updated
26 January 2015
Operator or applicant
REG Windpower
Planning authority
Dumfries and Galloway
Planning application reference
13/P/2/0189
Appeal reference
PPA-170-2096
Turbines
3
Address (REPD)
Between Castle Douglas and Kirkcudbright
Council area (by location)
Dumfries and Galloway
Time to decision
80 weeks
REPD reference
4606

Who decides

ApplicationsDumfries and GallowayUK
Decided applications (solar, wind, battery)10610,236
Refused40 (38%)19%
Solar refused1 of 1812%
Onshore wind refused33 of 7245%
Battery storage refused6 of 1616%
Median time from submission to decision60.9 weeks17.0 weeks
Appeals lodged / allowed19 / 17—

Other large projects within 10 km

ProjectTypeMWStatuskm
Barcloy Hill Wind Farmwind farm12.5refused on appeal1.2
Mayfield Community Wind Farmwind farm20.4refused on appeal2.3
Solar Park & Battery Storage at Little Drum Near High Bankssolar farm36approved, not built5.3
High Nunton Farm Solar Farm & Battery Storagesolar farm49.9approved, not built9.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.8641, -3.9731).