Energy Projects Near You

High Nunton Farm Solar Farm & Battery Storage (49.9 MW)

High Nunton Farm Solar Farm & Battery Storage is a 49.9 MW solar farm project in Dumfries and Galloway, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 22 January 2025, not yet built; the record was last updated on 26 June 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWsolar farm
approved, not builtstatus in REPD
26 June 2026record last updated
Dumfries and Gallowaycouncil area

Planning timeline

DateStage
7 January 2022Application submitted
22 January 2025Planning permission granted
22 January 2028Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
49.9 MW
Status (REPD)
approved, not built
Record last updated
26 June 2026
Operator or applicant
High Nunton Solar Limited
Planning authority
Dumfries and Galloway
Planning application reference
21/2490/FUL
Site area
48.9 ha
Address (REPD)
The South & NW/O High Nunton Farm, Steading, Borgue, Castle Douglas
Council area (by location)
Dumfries and Galloway
Time to decision
159 weeks
Name in REPD
High Nunton Farm - Solar Farm & Battery Storage
REPD reference
10532

The scheme also includes battery storage, recorded separately in REPD (approved, not built).

Who decides

ApplicationsDumfries and GallowayUK
Decided applications (solar, wind, battery)10610,236
Refused40 (38%)19%
Solar refused1 of 1812%
Onshore wind refused33 of 7245%
Battery storage refused6 of 1616%
Median time from submission to decision60.9 weeks17.0 weeks
Appeals lodged / allowed19 / 17—

Other large projects within 10 km

ProjectTypeMWStatuskm
Solar Park & Battery Storage at Little Drum Near High Bankssolar farm36approved, not built5.7
Knockendurrick Wind Farmwind farm14refused8.0
Chapmans Howe Wind Farmwind farm6.9refused on appeal9.5
Mayfield Community Wind Farmwind farm20.4refused on appeal9.8
Barcloy Hill Wind Farmwind farm12.5refused on appeal10.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.8228, -4.1037).